Construction Planner and Scheduler, Halliburton-Kellogg Brown & Root (HKBR), Syncrude UE-1 Project
START Date:
January, 2002
END Date:
April, 2004
Project time management of the Reactor and Burner, Diluent Recovery Unit and several site-wide work scope and contracts, support the preparation of CWP & Field Installation Work Packages (FIWP) covering foundation, insulation, electrical, refractory and fireproofing, development of level-4 construction schedule, earned value progress estimation, support field construction change management process, prepare schedule forecast tied to cost projection, collect direct and indirect field labors, back-charge and rework hours and costs. |
Experience Hours (Planning & Scheduling):
3000
Experience Hours (Cost Management):
950
Experience Hours (Forensic Analysis):
700 - Company: