Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Covered Steel Footbridge

Simple universal beam steel bridge in modular sections, welded on site. 16 truss sections each 15 m in length, supported on H-frame vertical columns / supports.

  • Support Steelwork Fabrication (4 bays) = 25 days
  • Support Steelwork Erection (4 bays) = 30 days
  • Truss erections (4 bays) = 18 days
  • Paintwork To Steel (16 bays) = 35 days
  • Bridge Deck Concrete Works (16 bays) = 60 days (staggered)
  • Bridge Lighting, Roof etc (16 bays) = 40 days
  • Bridge Finishing, Handrails and Grano = 14 days

Structural Steelwork...

Task / DescriptionSlow  Ave  Fast   Units
 Simple Universal Beam Steel Bridge, erect support steel H frames-  1.2 -   days/no
 Simple Universal Beam Steel Bridge, erect 15m truss-  3.3 -   m/day

Market Place

Primavera P6 and Microsoft Project books, on-line video training courses and training material available from an internationally recognised publisher. Teach yourself using on-line or book based learning or run your own in-house or public courses.