Rates, Norms & Durations

681
What is needed to come up with a production rate?

A duration of time, the manhours involved, and an amount of work produced?

This section is here to document this.  What information do you have that you can share?

Comments

Manual Rates

Hi,

It seems that the most of the rates here are equipment rates. do you have any rates for manpowered activities (e.g. manual excavation)

Productivity rates for "Civil Infra. and Oil & Gas Projcts

Dear Friends,

I need the productivity rates for "Civil Infrastructure and Oil & Gas Projcts" of Middle East Countries. Any one can help ? Please send the excel/word sheet to my e-mail id:

ramanannagamani@gmail.com

Thanks.

Ramanan

Drainage outputs

looking at the drainage outputs on here they don't seem to be that reliable? does anybody have an excel spreadsheet they would be able to send with some general drainage outputs?

ManPower Productivity Norms for MEP

hi,

Anyone having Manpower productivy norms excel file for MEP(Gulf), it will be very helful to me.

 

e-mail: hariveerendra@gmail.com

Drainage outputs

I am struggling to see any logic behind the productions per hour on the drainage?

33m per hour for 150mm drainage in runs exceeding 30m or greater is impossible - unless installed via trenchless methods!

I calculate my drainage productions to include dig, bed and surround, pipe laying and backfilling compacting in accordance with the specification and would never price on more than 30 - 35m per DAY for a 150mm UPVC pipe at a depth not exceeding 1m.

What do the productions on here realte to and what do they include?

Drainage outputs

I am struggling to see any logic behind the productions per hour on the drainage?

33m per hour for 150mm drainage in runs exceeding 30m or greater is impossible - unless installed via trenchless methods!

I calculate my drainage productions to include dig, bed and surround, pipe laying and backfilling compacting in accordance with the specification and would never price on more than 30 - 35m per DAY for a 150mm UPVC pipe at a depth not exceeding 1m.

What do the productions on here realte to and what do they include?

Contact JEPM LLC at 409-457-7725

What geographical location is labor being executed? (remote/local port)

What is the weather conditions?

What type of industry?

Other particulars or need; Are there readily available resource (MP & DFL Equip/Consumables) ?

Please feel free to contact me at your convenience. 

Once we come into mutual agreement, I will produce the needed excel loaded unit rates for your project/s need/s.  Based on execution industry actuals.

Best regard,

JEPM LLC

Project Controls Engineer SME

Jacob Armstrong

409-457-7725

Project Controls SME

Are you in need still?

Jaocb Armstrong JEPM LLC  409-457-7725

 

Ya, I am waiting for

Ya, I am waiting for comments. If you can give some feedback/ comments, it will greatly be useful.

Thanks/Regards,

Santhosh

Impact of crew size and composition on productivity

Ya, I am waiting for comments. If you can give some feedback/ comments, it will greatly be useful.

Thanks/Regards,

Santhosh

Project Controls SME

Are you in need still?

Jaocb Armstrong JEPM LLC  409-457-7725

Impact of crew design (crew size and composition)on productivity

Hi all,

Can you comment on impact of crew design, i.e crew size and composition on productivity?

Thanks,

Santhosh

Construction labour rates

Dear all experts;

This data is very useful for me and thank you all. But i need construction labour rates as an excel file. If somebody has it and sen me i will very be thankful. Also can you please give a book advise for this issue.

Thank you all.

efe.gurkan@hotmail.com

productivity rates

Dear all experts,

 

I need the productivity rates for Oil & Gas Project - Construction Trade like Sand Blaster, Fireproofer, Spray Painter, Scaffolder, Sheet Metal Fitter, Insulators and Welder.

I will be very thankful if excel file or PDF file of all production rates can be shared on my email address: sukh_shrestha@hotmail.com

Thank You

Productivity

Can i get the production rate dia Inch for CHW pipes for example 20" pipe one joint require 3 hours .. Etc or if there is a formula followed to calculate the same knowing that its all sch STND

Crew structure

Thank you deeply, for the great effort you've been doing.

I just would like to pay your attention that the productivity rates are in a big need to the crew structure producing these rates.

 

Best Regards,

Crew structure

Thank you deeply, for the great effort you've been doing.

I just would like to pay your attention that the productivity rates are in a big need to the crew structure producing these rates.

 

Best Regards,

Crew structure

Thank you deeply, for the great effort you've been doing.

I just would like to pay your attention that the productivity rates are in a big need to the crew structure producing these rates.

 

Best Regards,

Pluming Productivity rates

Dear all experts,

 

I need the productivity rates for first and second fixs for MEP work (HVAc, Firefighting and Plumbing).

 

Thank you

Pluming Productivity rates

Dear all experts,

 

I need the productivity rates for first and second fixs for MEP work (HVAc, Firefighting and Plumbing).

 

Thank you

Excel or PDF format of rates

Good Morning,

 

The information avaialble here is very useful for me, thanks a lot.

I will be very thankful if excel file or PDF file of all prodcution rates can be shared on my email address: lnt.vikas@gmail.com

Thanks,

Vikas Budhiraja, PMP

Productivity for Platform fabrication & installation

 

 

Can anyone help me with the units used to measure progress of platfrom fabrication & welding?

 

Is it ok to USE ... Kg of steel fabricated or welded?

Productivity for Platform fabrication & installation

 

 

Can anyone help me with the units used to measure progress of platfrom fabrication & welding?

 

Is it ok to USE ... Kg of steel fabricated or welded?

Partitions

Hi Guys,

 

Just like to know if we have productivity rate for glazing partitions..... also there is no productivity rate for plasterboard installation on the partitioning rates.

 

Thanks!

 

Ruel

MEP Productivity Norms

 

S.N0

Activity

Productivity norms

Qty

Units

DUCTING:

1

Duct

1.2 – 1.5

Sqm/man/day

2

Insulation

3

Sqm/man/day

3

1 No - VAV

3

Sqm/man/day

4

1 No - ECV

2

Sqm/ man/day

5

1 No – Joint Insulation

0.4

Sqm/man/day

6

1 No - Flexible Duct

1

Sqm/man/day

7

1 No - Plenum

1

Sqm/man/day

8

1 No - MSFD

2

Sqm/man/day

9

1 No - VCD

1

Sqm/man/day

10

Pressure Test per 25 Sqm ducting

4.5

Sqm/man/ day

11

Multipurpose Supports – 4 No

1.5

Sqm/man/day

12

Grills & Diffusers

6

No’s / Man/ day

13

Linear Slot Diffuser

6

Rm / Man / day

 

Kindly note that here ducting  is inclusive Support fixing + Cleat fixing + Sealant application

CHW PIPE:

1

1" – 2" dia

7.5

Rm/man/day

2

2" - 3"dia

5

Rm/man/day

3

4"dia

2.5

Rm/man/day

4

6"dia

1.5

Rm/man/day

5

8"dia

1.2

Rm/man/day

6

10"dia

1

Rm/man/day

7

CHW Pipe Insulation

15

Rm/man/day

8

Pressure Test for 100 Rm

3

man/day

9

Valve Package

1.5

Man / day / unit

 

Kindly note that here Chilled water piping is inclusive of Support fixing

S.N0

Activity

Productivity norms

Qty

Units

ELECTRICAL/ELV

1

Conduit

16

Rm/man/day

2

Wiring

30-40

Rm/man/day

3

Cable tray

5-6

Rm/man/day

4

Trunking

8-10

sq.m/man/day

5

DB Installation

1

Nos/man/day

6

DB Termination

1

Nos/man/day

7

Final Fix Accessories

8

Nos/man/day

8

Light points

8

Nos/man/day

PLUMBING

1

Water supply pipe installation

5

Rm/man/day

2

Drain pipe installation

3

Rm/man/day

Kindly note that Piping Installation is inclusive of Support fixing

Middle East MEP Worker Production rate

Hi all,

 

I am also facing problem in sourcing MEP labout production rate for Middle East Region. Anyone can help?

 

regards,

 

Kevin

Request for clarification....

Hi Frendz ...

I like this section this is helping me in may ways ..but i am facing problem when it comes to productivity rates given without resources, as what resource  should i consider if i want to use these rates please help .......

 

 

regards,

Khan