Trackwork

Trackwork...

Task / DescriptionSlow  Ave  Fast   Units
 FST Floating Track Slab, side restraints9.6 -  -   m/day
 FST Floating Track Slab, resin pads10.2 -  -   m/day
 FST Floating Track Slab, slab units10.6 -  -   m/day
 PCBT - Pre-cast Concrete Block Track, in Bored Tunnels17.1 41.0 -   m/day
 PCBT - Pre-cast Concrete Block Track, in Cut and Cover Tunnels-  35.0 -   m/day
 PCBT - Pre-cast Concrete Block Track, in Station Tunnels-  35.0 -   m/day
 IST - Isolated Slab Track, in Bored Tunnels-  20.0 -   m/day
 IST - Isolated Slab Track, in Cut and Cover Tunnels-  34.0 -   m/day
 IST - Isolated Slab Track, in Station-  29.0 -   m/day
 FST - Floating Slab Track, in Station3.6 4.6 5.7  m/day
 Ballasted Track, in Mainline57.0 71.0 115.0  m/day
 Ballasted Track, in Depot-  28.0 -   m/day
 Non-Ballasted Track, in Depot8.5 12.8 17.4  m/day
 Embedded / Paved Track, in Depot-  71.0 -   m/day
 Heavy Maintenance / Train Wash Track, in Depot-  29.0 -   m/day
 Maintenance Pit, in Depot-  52.0 -   m/day
 Siding Trackwork, in Depot-  38.0 -   m/day