Time Now

The time at which all progress information entered for a project should be correct as of this date. The time at which all remaining work starts.

This is the date when Progress is measured up to and generally coincides with the production of the Progress Report.

The date used in order to calculate the progress of the project. All estimates to complete or remaining durations should be assessed in accordance with the Progress Date.

Also known as Data Date in some software.

Market Place

See how the TIME - LOCATION - VIEW brings clearness to your work programmes
For 25+ years, APMX has been providing competency based project management training to Fortune 500 companies around the world, applying the principles of project based learning, designed to produce measurable results, generating a favorable “return on training investment”.
Primavera P6 and Microsoft Project books, on-line video training courses and training material available from an internationally recognised publisher and PMI accredited REP. Teach yourself using on-line or book based learning or run your own in-house or public PMI accredited courses.