Time Now

The time at which all progress information entered for a project should be correct as of this date. The time at which all remaining work starts.

This is the date when Progress is measured up to and generally coincides with the production of the Progress Report.

The date used in order to calculate the progress of the project. All estimates to complete or remaining durations should be assessed in accordance with the Progress Date.

Also known as Data Date in some software.