Beam Falsework Formwork

Rates include for making, fixing, cleaning and minor repair works etc, rates in m2/hr.

Soffits - On runners and props, including erection of props etc.

 

Hight of Beam Soffit--->      0 - 3.5 m3.5 - 5.0 m
WidthFixStrikeFixStrike
     
100 - 200 mm0.701.230.581.02
200 - 300 mm0.811.390.681.15
300 - 500 mm0.931.540.781.28
500 - 750 mm1.161.850.961.54
exc 750 mm1.232.171.031.82

 

Soffits - On runners and props, on previously erected props etc.  

 

Hight of Beam Soffit--->    0 - 3.5 m 3.5 - 5.0 m
WidthFixStrikeFixStrike
100 - 200 mm0.961.690.911.67
200 - 300 mm1.111.921.051.82
300 - 500 mm1.272.081.202.00
500 - 750 mm1.562.501.492.44
exc 750 mm1.642.861.392.70

 

 

Sides - Strutted from soffit bearers etc.

         

Hight of Beam Soffit--->    0 - 3.5 m 3.5 - 5.0 m
DepthFixStrikeFixStrike
100 - 200 mm0.781.230.741.18
200 - 300 mm0.931.390.881.32
300 - 500 mm1.061.541.021.47
500 - 750 mm1.472.081.392.00
exc 750 mm1.542.331.472.33

 

Sides - Using clamps and struts etc. 

Hight of Beam Soffit--->    0 - 3.5 m 3.5 - 5.0 m
DepthFixStrikeFixStrike
100 - 200 mm0.911.470.871.39
200 - 300 mm1.091.641.041.56
300 - 500 mm1.271.821.201.72