Check out our Assessment Centre and the Guild's Knowledge CAR and the Soteria Method

Primavera P6

How Early and Late date are calculated in Start to Start relationship in Primavera P6

In Finish to Start relationship, Primavera calculate Early and Late date base on 2 process

How is the Y-Axis scale determined in the Resource/Activity Usage Profile

In Primavera when we show Resource Usage Profile or Activity Usage Profile, the max value in Y-Axis is determined by software. And we may wonder how is it determined.

How to make a labor, equipment mobilization plan in Primavera P6

In a project plan beside the Start and Finish date of activity, we also need to know When we need resource, and How many resource we need.

I will show you how to do it.

How to perform Impacted As-Planned Delay Analysis in Primavera P6

The Impacted As-Planned method measures the impact of the delays on the as-planned schedule. The delays are formulated as activities and added to the as-planned schedule showing the effect of each delay and demonstrating how the project is being delayed. The amount of delay equals the difference in completion dates between the schedules before and after the impacts.

How to perform Time Impact Analysis / Window Analysis in Primavera P6

A Time Impact Analysis is a method used to determine extent of impact from potential delay in construction process. This schedule analysis method involves the insertion or addition of activities indicating delays or changes into an updated schedule representing progress up to the point when a delay event occurred to determine the impact of those delay activities.

Create P6 resources dictionary using excel without using SDK

The SDK (Software Development Kit) is an awesome tool that allow P6 database to connect to excel and exchange information in order to create the schedule using excel. But sometimes the SDK is not installed on the Primavera machine and the scheduler doesn’t have the privilege to install it or the resource sheet in the SDK is not working with P6 version that the scheduler has. In this article I will show you how to create the resources dictionary using excel and without the need to use the SDK or XER Parser tool.

 

How to update Baseline in Primavera P6

Baseline is something we usually do not change. However in some case we need to change it.

I will show you how to do it.

Detect changes made to calendars between two projects in P6

The Claim digger or Schedule Comparison is a widely used tool in P6 to compare between two projects and detect the differences.

One of the main shortage of the Claim Digger or the Schedule Comparison tool is detecting the changes in calendars.

The tool will not detect any revisions in calendars working hours or changing from Project to Global calendar if both have the same description.

Claim Digger will tell us nothing about calendars other than whether the name of the calendar is different.

Determine the longest path of a resource leveled schedule in P6

Unfortunately when it comes to resources and resource leveling, P6 model is absolute. P6 doesn’t calculate the float correctly and the longest path will not be accurate since the late and early dates will not change after leveling.

Primavera P6 doesn’t take in consideration the new dates after the leveling in calculating the total float or the longest path, to illustrate further if we have a project consists of three activities A,B & C and they all share the same resource and each activity 5 days duration and the project completion after 15 days.

The story behind the negative float in P6

The negative float is a very popular hot topic in the scheduling field and it’s generated when the late dates are less than the early dates and usually it’s accompanied with a delay in the project, and a lot of project management professionals think that the only reason for a negative float is because a constraint that has been used in the schedule. Although the first thing you look for when you see a negative float is the constraints that are applied to the schedule, but that not the only reason that generates the negative float in P6.

Market Place

The aim of this training is to provide delegates with a fundamental understanding of the Guild of Project Controls Planning and Scheduling skills level at the GPC Preparatory level.
See how the TIME - LOCATION - VIEW brings clearness to your work programmes
Primavera P6 and Microsoft Project books, on-line video training courses and training material available from an internationally recognised publisher and PMI accredited REP. Teach yourself using on-line or book based learning or run your own in-house or public PMI accredited courses.
For 25+ years, APMX has been providing competency based project management training to Fortune 500 companies around the world, applying the principles of project based learning, designed to produce measurable results, generating a favorable “return on training investment”.
Syndicate content