Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

P6

Primavera p6 WBS grouping bands in excel

PLeae find the below Youtube link for the video how to prepare color bands of WBS in excel with one click

https://youtu.be/1jByS22FXJY

Primavera Tips and Tricks - Tracing logic to a targeted activity using Primavera P6

Primavera Tips and Tricks

Tracing logic to a targeted activity using Primavera P6

Project Controls – Planning and Scheduling

July 2018 By David H. Doughty, PSP

Introduction:

In this post, I will show you how trace logic to a targeted activity on your project by utilizing Multiple Float Path functionality in Primavera P6.

How to use P6 various Percentages in Project Control?

Title: "How to use P6 various percentages in project control?"

Author: "Deyi.zhang/张德义"

How to use P6 to build a planning system for power plant construction?

Title: "How to use P6 to build a planning system for power plant construction?"

Author: "Deyi.zhang/张德义"

How to use P6 to realize interface management in large-scale engineering projects?

Title: "How to use P6 to realize interface management in large-scale engineering projects?"

Author: "Deyi.zhang/张德义"

Calculations of Summary Original Durations in Primavera P6

By Yaser A. Al-Bustanji CPCM, ACIArb, PMP, PMI-SP, PMI-RMP, November, 2017

Introduction

This article is a simple guide to understand the data stored in the P6 Original Duration fields that appear in all summary bands such as Project, WBS, Resources and Activity Codes.

How to define Resource Productivity in Primavera P6 and create schedule

When create a schedule, we can based on Resource Productivity to estimate duration.

For example:

  • We have a team which can cast 10 m3 of concrete per day (This is Productivity)
  • We have an Foundation which take 100 m3 concrete.
  • Duration of Foundation activity will be  100 / 10 = 10 days

Now we will do it in Primavera.

Supposed that we have a schedule like below picture:

Retain or Override – The question is logical

Title: Retain or Override – The question is logical

Author: Stephen J.C. Paterson

The P6 XER File Viewer You Didn’t Know You Needed

Edit; ScheduleReader™ (previously PrimaveraReader™) has been rebranded, please see http://www.planningplanet.com/advertisers/schedulereader

Moving from Primavera P3 to P6 EPPM

Author: "Moving from Primavera P3 to P6 EPPM"

Astract:

Moving from P3 to EPPM, this article defines the methodology around moving from the old Primavera P3 into the EPPM or P6 Professional environment.

Market Place

Primavera P6 and Microsoft Project books, on-line video training courses and training material available from an internationally recognised publisher. Teach yourself using on-line or book based learning or run your own in-house or public courses.
Syndicate content