Making Good Concrete
Rates including blowing out, preparations, clean and shutter joints and making a fair faced finish.
| By Hand | With Mechanical Sander | |
| Walls | 5.56 m2/hr | 8.62 m2/hr |
| Columns | 2.80 m2/hr | 6.99 m2/hr |
| Sides and Soffits of Beams | 2.80 m2/hr | 6.99 m2/hr |
| Soffits of Slabs | 4.21 m2/hr | 7.58 m2/hr |
| Vertical Bolt Holes | 16.67 no/hr | |
| Horizontal Bolt Holes | 14.49 no/hr | |
| Vertical Shutter Joints | 28.57 m/hr | |
| Horizontal Shutter Joints | 25.00 m/hr | |
| Rub Down Precast Concrete | 16.95 m2/hr |
| Scabble | ||
| Single head brush hammer | 0 - 4 mm | 30.74 hrs/m2 |
| 0 - 8 mm | 59.14 hrs/m2 | |
| Three head brush hammer | 0 - 4 mm | 37.14 hrs/m2 |
| 0 - 8 mm | 71.12 hrs/m2 |