Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Making Good Concrete

Rates including blowing out, preparations, clean and shutter joints and making a fair faced finish.                                               

  By Hand With Mechanical Sander
Walls 5.56 m2/hr 8.62 m2/hr
Columns 2.80 m2/hr 6.99 m2/hr
Sides and Soffits of Beams 2.80 m2/hr 6.99 m2/hr
Soffits of Slabs 4.21 m2/hr 7.58 m2/hr
Vertical Bolt Holes 16.67 no/hr  
Horizontal Bolt Holes 14.49 no/hr  
Vertical Shutter Joints 28.57 m/hr  
Horizontal Shutter Joints 25.00 m/hr  
Rub Down Precast Concrete 16.95 m2/hr  
   

 

Scabble    
Single head brush hammer 0 - 4 mm 30.74 hrs/m2
0 - 8 mm 59.14 hrs/m2
Three head brush hammer 0 - 4 mm 37.14 hrs/m2
0 - 8 mm 71.12 hrs/m2

Market Place

Primavera P6 and Microsoft Project books, on-line video training courses and training material available from an internationally recognised publisher. Teach yourself using on-line or book based learning or run your own in-house or public courses.