Preparatory Works

Strip Existing Wallpapers (3 layers) 5.00 m2/hr

Burn Off/Heat Strip Paintwork 1.00 m2/hr

Chemically Strip Paintwork 1.30 m2/hr

Prepare walls 14.20 m2/hr

Prepare door frame 25.00 m/hr

Prepare door 12.50 m2/hr