Floor Finishes

Floor Finishes

Task / DescriptionSlow  Ave  Fast   Units
 Granolithic Flooring-  3.1 -   m2/hr
 Terrazzo Flooring, in-situ-  3.6 -   m2/hr
 Terrazzo Flooring, pre-cast-  4.6 5.1  m2/hr
 Mosaic Tiling, 0.045x0.045m-  1.5 2.2  m2/hr
 Clay, quarry Tiles, small areas, much cutting-  0.8 1.1  m2/hr
 Clay, quarry Tiles, large areas, little cutting-  2.2 2.8  m2/hr
 Raised Floor System-  2.6 -   m2/hr
 Linolium/Thermo-Plastic Flooring-  3.1 5.0  m2/hr
 Thermo-Plastic Floor Tiles-  3.3 5.6  m2/hr
 Wood Block Flooring, lay blocks-  1.5 2.1  m2/hr
 Wood Block Flooring, sand and polish-  3.1 -   m2/hr
 Carpeting, Underlay & Gripper-  5.6 6.1  m2/hr
 Carpeting, Adhesive Fixing-  3.5 4.2  m2/hr
 Carpeting, Fully Fitted-  2.0 2.8  m2/hr
 Hardboard Sheeting Coverings, small areas-  3.7 4.1  m2/hr
 Hardboard Sheeting Coverings, large areas-  6.6 7.2  m2/hr
 Floor Sheeting Coverings, Lay Lino-  9.5 10.5  m2/hr