Help with Schedule Finish Dates

QUESTION:

In Open Plan Professional for some reason the Schedule Finish Dates are not matching the Actual Finish Dates.   The Activity is progressed and completed.   Actual Finish Date is filled out and the task marked as Complete.  There is 0 Remaining Effort.   When I move the Time Now date forward, the Schedule Finish Dates move with it (Actual Finish Date stays the same).

ANSWER:

On the time now advanced settings, there should be an option called something like "actual dates override logic". If that option isn’t enabled, I think out of sequence progress can cause issues like you describe.

Market Place

See how the TIME - LOCATION - VIEW brings clearness to your work programmes
Primavera P6 and Microsoft Project books, on-line video training courses and training material available from an internationally recognised publisher and PMI accredited REP. Teach yourself using on-line or book based learning or run your own in-house or public PMI accredited courses.
For 25+ years, APMX has been providing competency based project management training to Fortune 500 companies around the world, applying the principles of project based learning, designed to produce measurable results, generating a favorable “return on training investment”.