Time Impact Analysis

A method of Delay Analysis that analyses the effect of each Event incrementally and takes account of the status of the project or programme at the time the delaying event occurred, the changing nature of the Critical Path and the effects of action taken, or that should have reasonably been taken to Mitigate delays.