Relationship

Defines how one activity is related to another. A relationship can be one of four types and may include a lag time:

1. Finish to start (FS) activity cannot start until another is finished.

2. Finish to finish (FF) activity cannot finish until another is finished.

3. Start to finish (SF) activity cannot finish until another begins.

4. Start to start (SS) activity cannot begin until another starts