Internally

2 coats emulsion

- to plaster 8.00 m2/hr

- to brick/blockwork 6.00 m2/hr

1 mist, 2 emulsion

- to plaster 6.00 m2/hr

- to brick/blockwork 4.50 m2/hr

1 primer, 1 undercoat, 1 gloss

- to plaster 2.30 m2/hr

Undercoat

- to door frame 20.00 m/hr

Gloss

- to door frame 16.50 m/hr

Undercoat

- to door 7.14 m2/hr

Gloss

- to door 6.25 m2/hr

 

Market Place

Primavera P6 and Microsoft Project books, on-line video training courses and training material available from an internationally recognised publisher and PMI accredited REP. Teach yourself using on-line or book based learning or run your own in-house or public PMI accredited courses.
See how the TIME - LOCATION - VIEW brings clearness to your work programmes
For 25+ years, APMX has been providing competency based project management training to Fortune 500 companies around the world, applying the principles of project based learning, designed to produce measurable results, generating a favorable “return on training investment”.