Kitchen Installations

Installation Sequences

Industrial and Commercial installations usually commence when false ceilings, floorings and final decorations are substantially complete. 

Kitchen Hood Installations are done before false ceiling completion and kitchen equipment is done after the civil wall&floor finishes.

Installation Periods

Size Of Kitchen

Are of Kitchen

Installation Time

100 people

50 m2

3 weeks

500 people

150 m2

5 weeks

1,000 people

275 m2

8 weeks

 For individual installations...

 Ovens, friers and large mixers etc = 1 man day per item

Sinks, bain maries, washers etc = 2 man days per item

Commercial Kitchen

Task / DescriptionSlow  Ave  Fast   Units
 Overall Installation for 100 persons or 50m2-  3.0 -   wks
 Overall Installation for 500 persons or 150m2-  5.0 -   wks
 Overall Installation for 1000 persons or 250m2-  8.0 -   wks
 Install Ovens, friers and large mixers etc-  1.0 -   mandays
 Install Sinks, bain maries and washers etc-  2.0 -   mandays


 

 