Concrete Road surfacing

Task / DescriptionSlow  Ave  Fast   Units
 Concrete Road surfacing, Kerbs or Side Haunches-  0.4 -   m3/hr
 Concrete Road surfacing, 150mm thick-  12.5 -   m2/hr
 Concrete Road surfacing, 200mm thick-  7.7 -   m2/hr
 Concrete Road surfacing, 300mm thick-  6.7 -   m2/hr