OFC Laying

OFC Laying

By Using Concrete/Road Cutter Equipment

Resources

  • Survey Team of 4  (1 Suveyor , 3 Assistants)
  • Equipment with Operator and Helper
  • Cutting Line Marking team ( 2-3 Persons)
  • OFC cable laying team ( 4 Persons)
  • Splicing team (2  technicians )

Productivity

if everything is planned properly with adequate overlap of 3-4 days. 400-500m/day can be  achieved.

By using trenching machine

  • Equipment with Operator and helper
  • Mini Dozer with operator
  • OFC Laying laying team (6-8 persons)
  • Rest resources as per above

Productivity

If everything has planned properly with adequate overlap of 2-3 days. 250-300m/day can be achieved.

Market Place

Primavera P6 and Microsoft Project books, on-line video training courses and training material available from an internationally recognised publisher and PMI accredited REP. Teach yourself using on-line or book based learning or run your own in-house or public PMI accredited courses.
See how the TIME - LOCATION - VIEW brings clearness to your work programmes
For 25+ years, APMX has been providing competency based project management training to Fortune 500 companies around the world, applying the principles of project based learning, designed to produce measurable results, generating a favorable “return on training investment”.