Concrete Finishing

Concrete Finishing

Task / DescriptionSlow  Ave  Fast   Units
 Surface Finishing, Steel Float By Hand9.2 13.9 25.0  m2/hr
 Surface Finishing, Wood Float By Hand11.7 17.2 29.4  m2/hr
 Surface Finishing, Power Float13.9 20.8 37.0  m2/hr
 Surface Finishing, Light Brush on Trowel55.8 90.1 170.0  m2/hr
 Surface Finishing, Brush on Trowel Margin28.8 48.5 85.0  m2/hr
 Surface Finishing, Sprayed By Pump, expose aggregate65.0 95.0 145.0  m2/hr
 Surface Finishing, Wire Brush, expose aggregate15.0 25.0 30.0  m2/hr
 Making Good Walls, prepare, shutter, pour-  5.5 8.6  m2/hr
 Making Good Columns, prepare, shutter, pour-  2.8 6.9  m2/hr
 Making Good Sides of Beams, prepare, shutter, pour-  2.8 7.0  m2/hr
 Making Good Slab Soffits, prepare, shutter, pour-  4.2 5.5  m2/hr
 Making Good Bolt Holes, prepare, shutter, pour14.8 16.8 25.8  no/hr
 Making Good Rubdown Precast Concrete, prepare, shutter, pour-  18.0 -   m2/hr
 Making Good Scabble 3 head brush hammer, prepare, shutter, pour30.7 59.5 73.8  hrs/m2