Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Metal Decking

Metal Decking Systems

Usually carried out with a minimum of a 3 man gang with a labourer.

Large Roof Areas = 70 m2/day

Smaller or Complicated Areas = 28 m2/day

Metal Decking

Task / DescriptionSlow  Ave  Fast   Units
 Metal Decking, large areas-  70.0 -   m2/day
 Metal Decking, small or complicated-  28.0 -   m2/day
 Titanium Sheeted Roofs-  9.5 -   m2/day
 Copper Roofs, flat work-  3.0 -   m2/day
 Copper Roofs, sloping work-  2.7 -   m2/day
 Zinc Roofs, flat work-  2.4 -   m2/day
 Zinc Roofs, sloping work-  2.1 -   m2/day
 Aluminium Roofs, flat work-  2.8 -   m2/day
 Aluminium Roofs, sloping work-  1.9 -   m2/day
 Lead Roofs, flat work-  2.5 -   m2/day
 Lead Roofs, sloping work-  2.1 -   m2/day
 Lead Roofs, dormer cheeks-  1.3 -   m2/day
 Lead Roofs, flat gutters-  88.0 -   m/day
 Lead Roofs, flat copings-  76.0 -   m/day
 Lead Roofs, stepped gutters-  3.5 -   m/day
 Lead Roofs, shaped copings-  3.3 -   m/day
 Lead Roofs, cover step flashings-  3.2 -   m/day
 Lead Roofs, rooflight flashings-  0.8 -   no/day
 Lead Roofs, domed roof coverings-  0.7 -   m2/day

Market Place

Primavera P6 and Microsoft Project books, on-line video training courses and training material available from an internationally recognised publisher. Teach yourself using on-line or book based learning or run your own in-house or public courses.