Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Titanium Roofing

Titanium Roofing System 

Metal roof works are usually carried out with 2 men gangs of skilled labour.  The rates do not include for the timber backing structures etc. 

Titanium roof on multiple sub‑layers. 

Typical composite rate of 9.5 m2/day. 

Installation 

Typical timing and sequence of works.  This is for an order of 5,000 m2 (HK Station Upper & Lower Roofs)...    

Element

Week

Manpower

Temporary Works

0 - 2

5

Metal Decking

2 -  3

12

Gutter Subframe

3 -  6

6

Vapour Barrier

4 - 13

4

Rockwool

4 – 13

 44

Cement Board

4 – 13

6

Ice / Water Shield

4 – 13

4

Gutter Lining

6 -  9

4

Aluminium Cladding / Subframe

6 – 11

6

Titanium Cladding

8 – 17

17

Aluminium Pannelling

9 - 14

6

 

Market Place

Primavera P6 and Microsoft Project books, on-line video training courses and training material available from an internationally recognised publisher. Teach yourself using on-line or book based learning or run your own in-house or public courses.