Staircase Reinforcement

 

Activity

TASKS

Task - UOM

L - Barbender/Fitter (Mandays)

L - Helper (Mandays)

M

M

M

Staircase Reinforcement

Staircase Rein - Placing in Position & Binding - Using TMT Bars, Mild Steel, Tor Steel

Mt

0.32 Mandays/0.1Mt

0.34 Mandays/0.1Mt

Bars - Include 5% Wastage

Binding Wire : 5 kg/0.1Mt

Cover Blocks - 10No/0.1Mt

 

Staircase Rein - Straightening, Cutting (With Machine Cutting), bending - Using TMT Bars, Mild Steel, Tor Steel.

Mt

0.2 Mandays/0.1Mt

0.28 Mandays/0.1Mt

Bars - Include 5% Wastage

  
 

Staircase Rein- Straightening, Cutting (With Manual Cutting), bending - Using TMT Bars, Mild Steel, Tor Steel.

Mt

0.29 Mandays/0.1Mt

0.32 Mandays/0.1Mt

Bars - Include 5% Wastage

  

Market Place

EVA18 is the major UK event for Project Control knowledge, know-how and networking. EVA is a conference organised by a project management practitioner for project practitioners and stakeholders
A comprehensive product suite with the flexibility to meet the varying needs of everyone involved in running projects
A user guide and training manual written for professionals who wish to learn how to plan and control projects in an established Primavera Enterprise environment with or without Resources & Roles.
We want to build software that solves real problems, allow people to work more productive and happier.
The toolkit provides advanced analytical tools which can help identify areas of poor schedule quality at the click of a button.