Plastering
Plastering
Task / Description | Slow | Ave | Fast | Units |
Browning (undercoat), Internal Walls under 2.5m high | 2.2 | 2.8 | 3.1 | m2/hr |
Browning (undercoat), Internal Walls over 2.5m high | 2.1 | 2.6 | 2.8 | m2/hr |
Browning (undercoat), Reveals and Columns less than 100mm wide | 9.9 | 10.0 | 10.1 | m2/hr |
Browning (undercoat), Reveals and Columns 100-200mm wide | 5.2 | 5.4 | 6.4 | m2/hr |
Browning (undercoat), Reveals and Columns 200-300mm wide | 3.3 | 3.6 | 3.9 | m2/hr |
Covings | - | 5.0 | - | m/hr |
Skimming (topcoat), Internal Walls under 2.5m high | 6.1 | 6.7 | 7.3 | m2/hr |
Skimming (topcoat), Internal Walls over 2.5m high | 5.5 | 6.1 | 6.7 | m2/hr |
Skimming (topcoat), Reveals and Columns less than 100mm wide | 12.6 | 13.8 | 15.4 | m2/hr |
Skimming (topcoat), Reveals and Columns 100-200mm wide | 7.7 | 8.3 | 9.8 | m2/hr |
Skimming (topcoat), Reveals and Columns 200-300mm wide | 4.5 | 5.0 | 5.5 | m2/hr |
Plaster Board to Ceilings | 3.2 | 4.5 | 5.5 | m2/hr |
Plastering Ceilings, 1 Bonding, 1 Skimming | 1.1 | 1.7 | 2.4 | m2/hr |
Plastering Ceilings, Topcoat Skimming | 2.7 | 3.2 | 5.4 | m2/hr |