Plasterboard

Plasterboard

Task / DescriptionSlow  Ave  Fast   Units
 Boarding to Plaster dabs3.6 4.0 5.5  m2/hr
 Boarding to Stud-work/Metal Lathes4.0 5.0 6.7  m2/hr
 Boarding 12mm nailed to studding-  12.5 -   m2/hr
 Boarding 19mm nailed to studding-  16.5 -   m2/hr
 Tape, Jointing and Sanding-  0.1 -   hrs/m