Removable Ground Anchors

Removable Ground Anchors Recent innovation of "removable" ground anchor system. Steel cables are doubles up and threaded over a roller at the anchor end. Once de-stressed, they can be pulled out. 1 rig can achieve...

  • Drill 30 m shaft 7.0 hrs
  • Install strands/setup anchor 6.0 hrs
  • Grout in strands 2.0 hrs
  • Stressing can be done 4 - 7 days after grouting.

Usually at 3 m horizontal centres and can only be worked on with 5 - 6 m spacings. So a hit and miss method must be adopted, giving a significant programme constraint.

Market Place

Primavera P6 and Microsoft Project books, on-line video training courses and training material available from an internationally recognised publisher and PMI accredited REP. Teach yourself using on-line or book based learning or run your own in-house or public PMI accredited courses.
For 25+ years, APMX has been providing competency based project management training to Fortune 500 companies around the world, applying the principles of project based learning, designed to produce measurable results, generating a favorable “return on training investment”.
See how the TIME - LOCATION - VIEW brings clearness to your work programmes