Bentonite Waterproofing

Sheeting to be installed and covered over immediately in order to prevent drying out, carried out with a gang of at least 3 people.

  • Horizontal Surfaces = 25.0 m2/hr
  • Vertical surfaces = 15.0 m3/hr