Sheet Piling

Sheet Piling On reclamation, sand fill, sheet piling by crane and drop hammer, vibro hammer or diesel hammer.

  • A rate of 20 - 25 No/day to 20 to 35 m deep.
  • 1 no = 0.4 m wide on plan and 6 m long.
  • Therefore 8 - 10 m/day per rig is achievable.

On more difficult areas, such as through existing ground or a sea wall for example.

  • A rate of 10 - 12 No/day to 20 m deep.
  • Therefore 4 - 6 m/day per rig is achievable.

For more shallow sheet pile walls

  • Driven by - Pilemaster 60.0 m/day
  • Driven by - Automatic Drop Hammer 32.0 m/day

Steel for piles is usually readily available and a two week lead in is often all that is required.

Sheet Piling

Task / DescriptionSlow  Ave  Fast   Units
 Vibro/Drop Hammer, 10m deep Sand-  55.0 60.0  m/day
 Vibro/Drop Hammer, 35m deep Sand3.5 32.0 10.5  m/day

Market Place

Primavera P6 and Microsoft Project books, on-line video training courses and training material available from an internationally recognised publisher and PMI accredited REP. Teach yourself using on-line or book based learning or run your own in-house or public PMI accredited courses.
For 25+ years, APMX has been providing competency based project management training to Fortune 500 companies around the world, applying the principles of project based learning, designed to produce measurable results, generating a favorable “return on training investment”.
See how the TIME - LOCATION - VIEW brings clearness to your work programmes