Progress Reporting

Construction Director, BPMS Ltd, £200m hotel in Leicester Square

START Date: 
September, 2017
Construction Director using Asta Power Project to produce short and long range programmes for production and progress reporting
Experience Hours (Planning & Scheduling): 
100

Senior Cost and Planning Engineer, Egypt, Build Housing Project

START Date: 
January, 2019
END Date: 
June, 2019
  • Overseeing actual Progress versus the planned work  milestones by frequent site inspection.
  • Detemine all significant impact on the project schedule and inform the project manager accordingly.
  • Resposible to address the contractor of the need to adhere to the required sequences and duration of schedule activities.
  • recommends priorities for allocation in the event of cofliction demands and co-ordinates the transfer of resources as necessary.
  • Advice project manager of the necessary programs to contractors at site and check to ensure that their activitie
Experience Hours (Planning & Scheduling): 
200
Experience Hours (Cost Management): 
300
Experience Hours (Forensic Analysis): 
350

Senior Cost and Planning Engineer, Egypt, Build Energy city in Libya

START Date: 
April, 2010
END Date: 
November, 2018
  • Overseeing actual Progress versus the planned work  milestones by frequent site inspection.
  • Detemine all significant impact on the project schedule and inform the project manager accordingly.
  • Resposible to address the contractor of the need to adhere to the required sequences and duration of schedule activities.
  • recommends priorities for allocation in the event of cofliction demands and co-ordinates the transfer of resources as necessary.
  • Advice project manager of the necessary programs to contractors at site and check to ensure that their activitie
Experience Hours (Planning & Scheduling): 
4000
Experience Hours (Cost Management): 
10000
Experience Hours (Forensic Analysis): 
10000

Senior Cost and Planning Engineer, Egypt, Build Energy city in Libya

START Date: 
April, 2010
END Date: 
November, 2018
  • Overseeing actual Progress versus the planned work  milestones by frequent site inspection.
  • Detemine all significant impact on the project schedule and inform the project manager accordingly.
  • Resposible to address the contractor of the need to adhere to the required sequences and duration of schedule activities.
  • recommends priorities for allocation in the event of cofliction demands and co-ordinates the transfer of resources as necessary.
  • Advice project manager of the necessary programs to contractors at site and check to ensure that their activitie
Experience Hours (Planning & Scheduling): 
4000
Experience Hours (Cost Management): 
10000
Experience Hours (Forensic Analysis): 
10000

Senior Cost and Planning Engineer, Egypt, Build Energy city in Libya

START Date: 
April, 2010
END Date: 
November, 2018
  • Overseeing actual Progress versus the planned work  milestones by frequent site inspection.
  • Detemine all significant impact on the project schedule and inform the project manager accordingly.
  • Resposible to address the contractor of the need to adhere to the required sequences and duration of schedule activities.
  • recommends priorities for allocation in the event of cofliction demands and co-ordinates the transfer of resources as necessary.
  • Advice project manager of the necessary programs to contractors at site and check to ensure that their activitie
Experience Hours (Planning & Scheduling): 
4000
Experience Hours (Cost Management): 
10000
Experience Hours (Forensic Analysis): 
10000

Planning Engineer , RAY ENGINEERING LTD , MUMBAI, INDIA , Fabrication, Erection & Commissioning of Hydrogen plant at IOCL (Praxair site), Paradeep, Orissa

START Date: 
December, 2007
END Date: 
November, 2012

Coordinating with client and PMC; participation in technical review of design

Managing reviews and inputs for project planning and scheduling; preparing progress reports

Implementation of pro‐active quality improvement system

Assist designers and the project leader in budget estimation of construction Projects

 Invoicing

Experience Hours (Planning & Scheduling): 
10000

Planning Manager, Stefanutti Stocks, Kusile Power Generation Project

START Date: 
June, 2013

SSBR (Stefanuti Stocks & BasilRead JV) (15/07/2013 - Current)

Planning Manager

 

Kusile Project (Head of Planning Department)

 

Experience Hours (Planning & Scheduling): 
100
Experience Hours (Cost Management): 
50
Experience Hours (Forensic Analysis): 
100

Project Controls Manager, Morgan Sindall PLC, (various projects) @ all UK

START Date: 
July, 2008
END Date: 
June, 2012

Morgan Sindall PLC Project Controls Manager Ensure project controls best practices were understood and followed by the all project teams based at Heathrow. •Managed a portfolio of terminal refurbishment projects. •Put in place the project controls strategy, wrote and developed Project Controls Procedure. •Managed progress, actual cost, schedule and cost risk. •Configured Primavera P6 software, set up and maintained Primavera P6 programmes for all contracts including NEC contracts. •Delivered two projects matching the “Perfect Delivery” criteria.

Experience Hours (Planning & Scheduling): 
3000
Experience Hours (Cost Management): 
2000
Experience Hours (Forensic Analysis): 
3000

Planning Engineer, Tornado General Trading and Contracting, 1) Building Projects 2) Road Projects

START Date: 
April, 2016
END Date: 
July, 2016

Bid schedule, Claims, Schedule Control and Monitoring, Progress Reporting, Meeting Coordinator, Master Schedule

Experience Hours (Planning & Scheduling): 
250

Planning Engineer, Saudi Oger Ltd., 1) King's Palace Projects 2) Buildings 3) Infrastructure

START Date: 
November, 2014
END Date: 
November, 2015

Generate and Develop Bid Schedule, Master Schedule, Control and Monitoring Schedule, Reports, Schedule Analysis

Experience Hours (Planning & Scheduling): 
2000

Market Place

For 25+ years, APMX has been providing competency based project management training to Fortune 500 companies around the world, applying the principles of project based learning, designed to produce measurable results, generating a favorable “return on training investment”.
Primavera P6 and Microsoft Project books, on-line video training courses and training material available from an internationally recognised publisher and PMI accredited REP. Teach yourself using on-line or book based learning or run your own in-house or public PMI accredited courses.
See how the TIME - LOCATION - VIEW brings clearness to your work programmes
Syndicate content