Senior Planner

Senior Planner, Blackburn, Chubb Systems Ltd, Communication & Security systems NNC Laboratories

START Date: 
June, 2016
END Date: 
November, 2016

June 2016 to November 2016: Chubb Systems Ltd (First Group) – Senior Planning Engineer

Experience Hours (Planning & Scheduling): 
800

Senior Planner, AMEC, Paisley Council Headquaters

START Date: 
October, 2005
END Date: 
October, 2006

Senior Site Planner for Amec building New extension and full exisiting structure refurbishment of Paisley Council HQ (Value £40) Responsible for all planning duties including progress reporting and short term target planning Assisting Commercial department with procurement and delay analysis

Experience Hours (Planning & Scheduling): 
2000
Experience Hours (Cost Management): 
200
Experience Hours (Forensic Analysis): 
200

Senior Planner, B&M McHugh, Various NWR Projects

START Date: 
February, 2006
END Date: 
March, 2012

 

B&M McHugh

SENIOR PLANNING AND PROJECT MANAGEMENT CONSULTANT

 

Oct 2011 – Feb 2012

Building, Civil and Environmental Contractor for both major and minor works:  East Anglia, Kent, Sussex, Wessex regions

Experience Hours (Planning & Scheduling): 
12000
Experience Hours (Cost Management): 
12000
Experience Hours (Forensic Analysis): 
4200

Senior Planner, CH2M Hill, Thames Tideway Tunnel

START Date: 
November, 2014
END Date: 
September, 2017
Project to build a large sewer across London, beneath the River Thames. Senior Planner for the Thames Water funded works (budget ≈£100m), successfully lead the restructuring of the planning department, and produced the strategic integrated schedule to aid interface management and manage risks through QSRA. Developed the project WBS, schedule reporting hierarchy and sitephasing plans, and was responsible for the forensic analysis of complex compensation events.
Experience Hours (Planning & Scheduling): 
6000
Experience Hours (Cost Management): 
2000
Experience Hours (Forensic Analysis): 
3000

Senior Planner, ISGEC JOHN THOMPSON, Noida (India) , Head Office & Sustaniable Development Projects

START Date: 
November, 2001
END Date: 
January, 2004

Collation of all estimates to prepare levels 1 and 3 networks on the hook-up and commissioning of the facilities for the Rough Storage Project.

 

Allocating task sheets into their work packs. Co-ordinate and collect all daily and weekly progress for all disciplines and phases, input to Artemis 9000, generating all schedules and reports, tabulations, 'S' curves and forecasts for Supervisors, OIM and Base Management.

 

Total working experience on Primavera 6

Experience Hours (Planning & Scheduling): 
4000
Experience Hours (Cost Management): 
700
Experience Hours (Forensic Analysis): 
250

Senior Planner , Leighton India Contractor Pvt. Ltd., Expansion of MPT Barmer Cairn Project

START Date: 
March, 2012
END Date: 
April, 2014

EPC Project Planning, Site Planning, Progress reporting (Daily Weekly monthly), Weekly and monthly meetings, Presentation, Invoic certification and approval, Sub-contract management, day to day Planning for site activities, resource management, micro scheduling for critical palth, P6 schedule devlopment and weekly updation, Devloped Progress measurement system, monitoring project control activities, etc.

Experience Hours (Planning & Scheduling): 
3000
Experience Hours (Cost Management): 
2050

Senior Planner, Cargill, Production Capacity Increase L1 & L2

START Date: 
August, 2017

Planning Manager responsible for development of Master Programmes for several projects running concurrently. Liaising with Client and Senior Team members to develop scope and integrate into Master Programme. S-Curve analysis, project tracking, programme updates and amendments. Rescheduling, identification & analysis of critical path and recommendations to target CP tasks in order to meet original target end date.

Experience Hours (Planning & Scheduling): 
800

Senior Planner, Alfred McAlpine Major Projects, Banstead Prison

START Date: 
October, 1989
END Date: 
March, 1992

Planning Manager responsible for development of Master Programme with manpower and materials resources. Development of Level 3 Programme, daily monitoring of progress, weekly and monthly reporting, coordination of contractors using project controls. Submission of delay claims based on resource histograms and resource levelling. Project involved 16 no. separate buildings interlinked through men, materials, pre-formed shuttering.

Experience Hours (Planning & Scheduling): 
5400
Experience Hours (Forensic Analysis): 
200

Senior Planner, SNC Lavalin, RBM Tailing Treatment Plant ; Kamoto Roaster Upgrade

START Date: 
November, 2011
END Date: 
October, 2012

Kamoto Scope – Brownfield

 

Experience Hours (Planning & Scheduling): 
1800
Experience Hours (Cost Management): 
750

Market Place

For 25+ years, APMX has been providing competency based project management training to Fortune 500 companies around the world, applying the principles of project based learning, designed to produce measurable results, generating a favorable “return on training investment”.
Primavera P6 and Microsoft Project books, on-line video training courses and training material available from an internationally recognised publisher and PMI accredited REP. Teach yourself using on-line or book based learning or run your own in-house or public PMI accredited courses.
See how the TIME - LOCATION - VIEW brings clearness to your work programmes
Syndicate content