Senior Planner

Senior Planner, FMC Technologies, Chevron wheatstone Subsea Production System

START Date: 
January, 2011
END Date: 
November, 2015
Planning and Monitoring of Subsea Systems for ENI Jangkrik Project from Jan 2014 Planning and Monitoring of Subsea Systems for Chevron Wheatstone Project from Jan 2012 to Dec 2013 Planning and Monitoring of Connections Systems for TOTAL CLOV from Jan 2012 to Oct 2012 Planning and Monitoring of Connections systems for Visund Sor / Katla / Hyme / Vigdis from Mar 2011 to Oct 2012
Experience Hours (Planning & Scheduling): 
10000
Experience Hours (Cost Management): 
3000
Experience Hours (Forensic Analysis): 
2000

Senior Planner, FMC Technologies, Chevron wheatstone Subsea Production System

START Date: 
January, 2011
END Date: 
November, 2015
Planning and Monitoring of Subsea Systems for ENI Jangkrik Project from Jan 2014 Planning and Monitoring of Subsea Systems for Chevron Wheatstone Project from Jan 2012 to Dec 2013 Planning and Monitoring of Connections Systems for TOTAL CLOV from Jan 2012 to Oct 2012 Planning and Monitoring of Connections systems for Visund Sor / Katla / Hyme / Vigdis from Mar 2011 to Oct 2012
Experience Hours (Planning & Scheduling): 
10000
Experience Hours (Cost Management): 
3000
Experience Hours (Forensic Analysis): 
2000

Senior Planner, FMC Technologies, Chevron wheatstone Subsea Production System

START Date: 
January, 2011
END Date: 
November, 2015

Planning and Monitoring of Subsea Systems for ENI Jangkrik Project from Jan 2014 

Experience Hours (Planning & Scheduling): 
10000
Experience Hours (Cost Management): 
3000
Experience Hours (Forensic Analysis): 
2000

Senior Planner, WS ATKINS Partners & Overseas, Etihad Rail- Stage 1, Riyadh Metro, Dubai Metro Project, Doha Metro

START Date: 
November, 2010

1.

Experience Hours (Planning & Scheduling): 
16950
Experience Hours (Cost Management): 
1000
Experience Hours (Forensic Analysis): 
4050

Senior Planner, CTEC, Merredin Power Station, West Angeles Power Station

START Date: 
July, 2011
END Date: 
January, 2012

CTEC Pty Ltd:  Senior Project Planning & Controls – Merredin Power Station – Greenfield Site

 

Experience Hours (Planning & Scheduling): 
1500
Experience Hours (Cost Management): 
900
Experience Hours (Forensic Analysis): 
500

Senior Planner, O'Donnell Griffin, All Great Western Region Projects

START Date: 
January, 2012
END Date: 
May, 2012

O’DONNELL GRIFFIN:   Senior Project Planner/Asst PM – Brockman 4 Phase 2 Expansion Project (FIFO) – project upwards of AUD$20mm

 

Experience Hours (Planning & Scheduling): 
900
Experience Hours (Cost Management): 
400
Experience Hours (Forensic Analysis): 
250

Senior Planner, Calibre Global, Turee Syncline, Yandi, Koodaideri Mine to Port transfer project

START Date: 
August, 2012
END Date: 
January, 2013

CALIBRE GLOBAL PTY LTD:  Senior Planner – Brockman 4 Phase III FEED/Koodaideri Bid-Tender/Yandi Engineering/Turee Syncline – Projects ranging from AUD$80mm to AUD$500mm.

Experience Hours (Planning & Scheduling): 
650
Experience Hours (Forensic Analysis): 
100

Senior Planner, VVB Engineering, Crossrail / Network Rail

START Date: 
March, 2016
END Date: 
June, 2018
Position: Senior Project Planner, MEP Project 1: Corssrail Anglian M&E works from Stratford to Shenfield -13 Stations and Tail Line. Project 2: Crossrail Woolwich Station Box, Portals and Connaught Tunnel Shaft. Client: Crossrail / Network Rail Employed by: VVB Engineering Job responsibilities:  Prepared schedule for MEP scope of work for Electrical HV, LV line, 200 Rooms CMS and Fixtures along the Mechanical (Plumbing, Drainage and Sump pump) work.

Senior Planner, VVB Engineering, Crossrail / Network Rail

START Date: 
March, 2016
END Date: 
June, 2018
Position: Senior Project Planner, MEP Project 1: Corssrail Anglian M&E works from Stratford to Shenfield -13 Stations and Tail Line. Project 2: Crossrail Woolwich Station Box, Portals and Connaught Tunnel Shaft. Client: Crossrail / Network Rail Employed by: VVB Engineering Job responsibilities:  Prepared schedule for MEP scope of work for Electrical HV, LV line, 200 Rooms CMS and Fixtures along the Mechanical (Plumbing, Drainage and Sump pump) work.

Senior planner, Tecnimont S.p.A., Chemical Plants

START Date: 
January, 2007

The homeoffice activities are:

Market Place

Primavera P6 and Microsoft Project books, on-line video training courses and training material available from an internationally recognised publisher and PMI accredited REP. Teach yourself using on-line or book based learning or run your own in-house or public PMI accredited courses.