# Senior planning engineer

# Senior planning engineer, Afcons Infrastructure Ltd, The South Connector Project

START Date: 
June, 2013
END Date: 
November, 2023

At present I am working in webuild SSA as a Planning Engineer in NEOM Project, Saudi Arabia.

AFCONS Experience:-

Previously i was worked Manager MIS in that I involved with planning & costing of 12 km TBM tunnel, 2Km NATM Tunnel & 6 underground metro stations including Architectural finishing Project, Delhi Metro (DC-05), Delhi India.

Experience Hours (Planning & Scheduling): 
6000
Experience Hours (Cost Management): 
12000
Experience Hours (Forensic Analysis): 
200

# Senior planning engineer, Webuild.SSA, The South Connector Project

START Date: 
June, 2023

At present I am working in webuild SSA as a Planning Engineer in NEOM Project, Saudi Arabia.

AFCONS Experience:-

Previously i was worked Manager MIS in that I involved with planning & costing of 12 km TBM tunnel, 2Km NATM Tunnel & 6 underground metro stations including Architectural finishing Project, Delhi Metro (DC-05), Delhi India.

Experience Hours (Planning & Scheduling): 
6000
Experience Hours (Cost Management): 
12000
Experience Hours (Forensic Analysis): 
200

# Senior planning engineer, Global Marine, Vattenfall Dan Tysk 2

START Date: 
February, 2021
END Date: 
January, 2022

Vattenfall Dan Tysk Offshore Windfarm – Integrated P6 planning, progress measurement and schedule analysis for a twenty HV/FO inter array cable replacement project comprising of survey operations, cable recovery, cable lay, cable jointing, termination & testing, rockdumping, CPS installations, cable trenching & burial operations and CTV operations. Also, planning services for SSEN Skye to Harris 33kV interconnector cable replacement project and SSEN ED1 cable replacements for Mull-Coll, Orkney-Hoy and Carradale-Arran Scottish islands interconnectors.

Experience Hours (Planning & Scheduling): 
2000
Experience Hours (Forensic Analysis): 
400

# Senior planning engineer, Nael and Bin Harmal Hydroexport - Qatar, Infrastructure Project

START Date: 
January, 2010
END Date: 
May, 2011

Tendered and Awarded Project:
•     LOGISTICS VILLAGE QATAR PHASE 1
Location: Industrial Estate, Al Wukair, Qatar
Contract Amount : QR 63.70 Million
Client: Gulf Warehousing Company
Consultant: Gulf Engineering and Industrial Co.

Project Duration: 12 months
Scope of Works:
1.     Earthworks
2.     Kerbing and Paving Blocks
3.     Storm Water Drainage
4.     Water Works