Progress Reporting

Planning Engineer, Tornado General Trading and Contracting, 1) Building Projects 2) Road Projects

START Date: 
April, 2016
END Date: 
July, 2016

Bid schedule, Claims, Schedule Control and Monitoring, Progress Reporting, Meeting Coordinator, Master Schedule

Experience Hours (Planning & Scheduling): 
250

Planning Engineer, Saudi Oger Ltd., 1) King's Palace Projects 2) Buildings 3) Infrastructure

START Date: 
November, 2014
END Date: 
November, 2015

Generate and Develop Bid Schedule, Master Schedule, Control and Monitoring Schedule, Reports, Schedule Analysis

Experience Hours (Planning & Scheduling): 
2000

Planning responsible #planningengineer #claims #projectcontrols #pcglobal #planningplanet #guildofprojectcontrols #disputes #jobs #disputereolution #planning #projectplanner #construction #pcg #plan, OAS Construtora, Trinidad and Tobago, Sir Solomon Hoch

START Date: 
September, 2014
END Date: 
June, 2016

-->Estimated quantities and cost of materials and equipment for civil/structural components (bridges, drainage and crash barriers) to determine project feasibility

-->Prepared regular interval progress reports regarding earthwork, asphalt, structural and storm-water systems using Microsoft Office and AutoCAD

-->Digitally archived weekly progress and technical “Knowledge Base” photographs of all sites and projects.

-->Assisting in the Planning/Scheduling of works and updating the Monthly production reports which interpret Planned vs. Executed quantities

Experience Hours (Planning & Scheduling): 
1000
Experience Hours (Cost Management): 
500
Experience Hours (Forensic Analysis): 
500

Planner/Scheduler, Junior Sammy Contractors Limited, & Oil & Gas Projects 2) Buildings 3) Infrastructure

START Date: 
January, 2017

--> Developing work schedules & quantity takeoffs for varying services (Civil/Structural, duct banks, manholes, underground piping and drainage systems)

--> Monitoring both on and off-site progress for both Civil/Underground Piping work at Union Industrial Estate and Corridor/Berth (port) operations, La Brea

--> Engaging with site teams of varying services to minimize interface delays.

--> Reviewing plans and specifications for effective schedule development.

Experience Hours (Planning & Scheduling): 
4000
Experience Hours (Cost Management): 
250
Experience Hours (Forensic Analysis): 
250

Project Engineer, Avida Land Corp. (An Ayala Land Company) and Filinvest Land Incorporated, Residential and Infrastructure Developments

START Date: 
October, 2004
END Date: 
June, 2007
  • Project management, construction planning and scheduling, site operation, quality control and safety implementation of all phases of construction works.
  • Reviewed, checked and evaluated Contractors construction schedule, quantities, variation orders and progress payment applications.
  • Assessed the impacts of design or construction changes and determined the cost and time implications.
Experience Hours (Planning & Scheduling): 
3000
Experience Hours (Cost Management): 
3000
Experience Hours (Forensic Analysis): 
1000

Planning Engineer, Laing O’Rourke Construction Hong Kong Limited, Express Rail Link (XRL) Contract 810B - West Kowloon Terminus Station South

START Date: 
January, 2012
END Date: 
March, 2013
  • Provided reports regularly to Top Management and Client.
  • Planned, developed and maintained schedules and associated resources.
  • Updated Project Controls Report for company-wide integrated Project Controls System.
  • Performedprogramme analysis and scenario studies to design changes, construction sequences, resources requirement, productivity rates, logistics planning and procurement.
  • Organized and facilitated planning sessions with project teams for schedule variances that impact milestone key dates and concluded remedial action plans.
  • Monitored crit
Experience Hours (Planning & Scheduling): 
2500

Senior Planning Engineer, MMC Gamuda KVMRT (PDP) Sdn Bhd, Klang Valley Mass Rapid Transit Line-1: Sungai Buloh - Kajang (SBK)

START Date: 
April, 2013
END Date: 
March, 2017
  • Civil Infrastructure Programme Management of:
    • Elevated Packages– viaduct structures, stations, depots and car parks;
    • SSP Spur line– viaduct structure connection of SBK (Line-1) to SSP (Line-2) depot with 0.55km viaduct (two single track line – 0.30km & 0.25km length);
    • SSP Depot1– additional stabling yard to existing SBK Sungai Buloh depot.
  • Provided reports regularly to Top Management and Client.
  • Developed and updated Project Dashboard and Time Chainage programme.
  • Reviewed, evaluated and monitored th
Experience Hours (Planning & Scheduling): 
8000
Experience Hours (Forensic Analysis): 
1000

Project Controls Engineer, Mitsubishi Heavy Industries, Ltd, Doha Metro Project Phase-1 MSI Contract – Systems, Rolling Stock, Trackwork and Depot

START Date: 
March, 2017
  • Planning and Project Controls of Red Line Metro Depot and Green Line Stabling Yard.
  • Provide reports regularly to Top Management, Consultant and Client.
  • Update Project Dashboard as per Qatar Rail Project Management Office requirement.
  • Integrate various programme and their associated interfaces in Project Master Schedule.
  • Analyze and evaluate performance (KPI’s) against an established schedule.
  • Initiates templates and improves reporting system to meet specific project requirements.
Experience Hours (Planning & Scheduling): 
4000

Senior Planning Engineer, BIZVILLE PROJECT MANAGEMENT Limited, Crude/Condensate Tank, FPSO Valve Hot-bolting Shutdown Maintenance Project (Client: Exxon Mobil), Various Projects: Community and RA Portfolio (Client: NLNG-Nigeria), Weir Tank and Skimmer Tan

START Date: 
October, 2017

*Portfolio Planner in charge of RA and Community Portfolio (Various Projects)
*Project Planning, Progress Tracking and Reporting, Schedule Risk Analysis and Claims Analysis for Projects.
*Develop In-house NLNG Schedule based on Portfolio Opportunity Realization Life Cycle: Identify, Assess, Select, Define and Execute.
*Resource Loading of schedule with Cost/Manhours and Develop Progress Measurement System(PMS).
*Prepare Weekly and Monthly Progress and Delay Analysis Report and Dashboards for the Project Leadership.

Experience Hours (Planning & Scheduling): 
3150
Experience Hours (Cost Management): 
3150
Experience Hours (Forensic Analysis): 
3150

Scheduling Enginner, SNC Lavalin, Multiple Projects

START Date: 
December, 2008
END Date: 
November, 2011

Planning Enginner - SNC Lavalin

- Build and Review Engineering Projects Schedules

- Build Engineering Services Schedules

- Build Projects Master Schedules with Basis of Schedules

- Review and improve Project Scheduling Standards

- Preparation of CAPEX in Civil and Piping Cost Estimates and Indirect Cost

- Project Management Software implementation and Change Management

Experience Hours (Planning & Scheduling): 
4450
Experience Hours (Cost Management): 
2200