Senior Planning & Cost Engineer, Consolidated Contractors International Company (CCC) of Greece, Construction of 4th Main Oil Line for New Main Oil Line Project

START Date: 
December, 1995
END Date: 
November, 1996

SENIOR PLANNING & COST ENGINEER in

                                                    Consolidated Contractors Int’l Company [CCC] of Abu Dhabi, UAE

              Project                                     :       Construction of 4th Main Oil Line for New Main Oil Line Project

              Place                                        :       Habshan to Jebel Dhanna, Abu Dhabi, United Arab Emirates      

              Client                                       :       Abu Dhabi Company for Onshore Oil Operations (ADCO)

              Value                                       :       UAE Dirhams Eighty (80) Million i.e. US Dollars 22 Million

Scope of Work of the project:

Construction of 113 km. of pipeline of 36” diameter, facilities for pig launcher, signalers & receiver and it’s installation. 24” diameter spur lines, sectionalizing valves & interconnecting jumpers by using hot tapping & stoppling techniques. Installation of chemical inhibition & mobile biocide injection packages. Civil works, Piping, Cabling, Earthing & Lighting at stations. Flow measurement & control by providing flow meters, pressure & temperature transmitters / gauges, flow control & pressure safety / relief valves. Software changes & hardware modifications to existing DCS.

                            Duties & Responsibilities

                        1)    Planning, Scheduling, Progress Measurement  & Schedule Control [using Primavera Project Planner(for DOS), Microsoft Excel &Word] by preparing & updating following:

                                    a)    Summary Project Schedule (Level - 1) with Work Breakdown Structure. Progress Measurement System.

b)       Control Schedule (Level - 2), Progress Curves, Working Schedule (Level - 3), Cash Flow Charts, Invoices.

c)       Manpower & Plant/Equipment deployment schedules / histograms. Material Procurement Schedule.

                            2)    Preparing & Updating Progress Reports viz. Daily Report, Weekly Report, Monthly Progress & Cost Report.