Lead Planning Engineer, Marathon , Brae A Rig Reactivation

START Date: 
January, 2012
END Date: 
September, 2013
Lead/ Senior Planning Engineer on the Brae Alpha Rig Reactivation Project preparation for decommissioning, (brownfield) • Achieved a fully integrated plan for Marathon combining the scopes for Archer Drilling and Petrofac. This covered the delivery of engineering, procurement, onshore equipment refurbishment, fabrication, offshore piece small destruct, stick build equipment installation, loop checking commissioning. This involved setting work break down structure, reporting structures & formats and integration with the platform schedules. I was closely involved in the management of subcontracted work scopes from the manufacture specific standalone packages like an HPU for the BOP lifting, the replacement BOP lifting frame, accumulator bottles to pipe fabrication and piece small structural items, mud gutters, supporting steel for drag chains, stair towers and walkways. The actual decommissioning of the Brae A platform was considered as a ‘stick de-construct’ this was shelved.