%100- Project Planning; Progress Reporting; Primavera P6

planning engineer, Larsen and Toubro Limited - ECC Division, Hyderabad Metro Rail Limited-Stations

START Date: 
April, 2012
END Date: 
September, 2013
Client billing, measurement of quantities, Preparationof BBS.Scheduling, preparation of Casting Plan. Lending technical support to execution team.Preparation of MIS reports, various Checklists.Tracking erection of precast segments.
Experience Hours (Planning & Scheduling): 
3000
Experience Hours (Cost Management): 
750

Cost and Planning Engineer, ENAC, PIPING

START Date: 
March, 2009
END Date: 
March, 2012

Pipeline project Ø 16" (95 Km)- Wilaya de TOUGGOURT- ALGERIA.
Pipeline project GREO Ø 28" (81 Km) - Wilaya de BATNA-M’SILA- ALGERIA
Missions: Planning on MS Project
Development of project budgets.
Performance monitoring.
Preparation of various reports.

Lead System Engineer and AIV manager, National Solar Observatory, Daniel K. Inoye Solar Telescope

START Date: 
May, 2012

Lead System Engineer and AIV manager for the Daniel K. Inouye Solar Telecope currently being installed on Haleakala Maui.  First light currently scheduled for Q3 2019.

Advisor - Planning and Scheduling, OPI International Nig. Ltd, Central Fault Block Extension Well Head Platform (CFBX WHP) &Okwok Wellhead Platform Jacket (OKWOK WHP

START Date: 
March, 2014
END Date: 
February, 2015

 

OPI international nig limited

Position:          Project Planning

Project:            Central Fault Block Extension Well Head Platform (CFBX WHP) &Okwok Wellhead Platform Jacket (OKWOK                          WHP)

Client:              Afren Energy Resources Limited

Experience Hours (Planning & Scheduling): 
1600
Experience Hours (Cost Management): 
250
Experience Hours (Forensic Analysis): 
300

PLANNING ENGINEER, Keppel Group, DNSTW

START Date: 
November, 2013
  • Created Work Breakdown Structure (WBS), input project activities, determined activity durations, and logic relationships.
  • Prepare and update project schedule based on the contract.
  • Created milestones to identify the start of work including activities that required constraints.
  • Monitored and updated project progress on a routine basis against established scope, schedules and budgets
  • Monitor critical activities based on the project schedule and advise project management.
  • Monitor day to day work progress and prepare the weekly and monthly program an
Experience Hours (Planning & Scheduling): 
18200
Experience Hours (Cost Management): 
10850
Experience Hours (Forensic Analysis): 
9650

Assistant Planning Engineer, IOT ENGINEERING PROJECTS LTD, 1X300MW MCCPL Power Project, COAL FIRED HETER, OIL& GAS Projects Infrastructurus Storage tanks, THERMAL POWER PLANT 600MW

START Date: 
July, 2007
END Date: 
August, 2014

ü  Preparation of planning schedule at different levels.

ü  Recourse Planning & assignment,Interaction with field personnel for developing schedule activities.

ü  Baseline Schedule preparation and progress comparison.

ü  Preparing Daily/weekly/Monthly progress reports & update.

ü  Preparation/updating of progress 'S' curves for reporting progress to Client/Management.

Experience Hours (Planning & Scheduling): 
15000
Experience Hours (Cost Management): 
2000

Assistant / Planning Engineer, Ali & Sons Contracting , Emal Abudhabi.

START Date: 
March, 2013
END Date: 
July, 2014
 Preparation, submission and updating of the project master Programme Preparation, submission, follow up and updating of :o Project detailed construction Programmeo Project material procurement scheduleo Project shop drawings scheduleo Project cost loaded scheduleo Project labor histogramso Project short term Programme (daily, weekly, monthly) Preparation, submission, Follow up subcontractors’ Programme of Works. Initiation/responding to all planning/time related correspondence to Engine
Experience Hours (Planning & Scheduling): 
1200
Experience Hours (Cost Management): 
600
Experience Hours (Forensic Analysis): 
800

Junior Site Planner, SOCOBAT, OMV CPF Block S2 Project

START Date: 
January, 2016

Ø  Internal and external project reporting (daily-weekly-monthly reports).

 

Ø  Tweekly look ahead schedule/ planning updating/ variance calculation and analysis

 

Ø  Manpower and Equipment mobilization schedule  

 

Ø  Costs and expenses estimation.

Assistant Construction Planner/Scheduler; Maintenance Planner, BPXA, Activity Planning

START Date: 
November, 2007
END Date: 
June, 2016

BPXA

Scheduler on the North Slope, Prudhoe Bay, Alaska.

Scheduled Facility Maintenance in P6 for Activity Planning program.

Integrated Projects with Facility Maintenance and 3rd Party contractors.

North Area Scheduer for four Assets in Prudhoe Bay.

Performance Planning Team Lead for Integrated Facility Planning initiative.

Experience Hours (Planning & Scheduling): 
16000