Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Senior Planner, Technical Office Engineer, Site Engineer at site, Egyptian Arab Contracting, Sanhour, ...

START Date: 
February, 1995
END Date: 
November, 1999

- Egyptian Arab ContractingFrom 1 Feb 1995 till 14 Nov 1999

a) From Apr 1998 till 14 Nov 1999 In SANHOUR Irrigation Project, This Project consists of under ground irrigation PVC pipes, Open Block Channels, Small Bridge, Regulator, and Meska Pump Station. The project value about 16,000,000 Egyptian Pounds.

My Duties:

·  As a Senior Site Engineer

·  Make the Time schedule for the project

------------------------

b) From 1 Feb 1995 Till 31 Mar 1998 In head office

My Duties:

·  Planning, Time Schedule and follow up the project of north delta in Egypt.

·  Make Monthly progressing reports.

·  Make Data Base for the projects ( Letters, Submittals, RC Casting,..)