Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Project Planning & Scheduling; Cost control; Performance Monitoring; Progress Reporting

Senior Planner, Free Lance, Several (analysis)

START Date: 
March, 2017
END Date: 
December, 2017

Searching for ERP and new tools for planning/scheduling.

Experience with 4D/5D simulation and construction planning.

Experience with Forensic claims analysis.

Experience Hours (Planning & Scheduling): 
150
Experience Hours (Cost Management): 
0
Experience Hours (Forensic Analysis): 
350

Lead Cost Engineer / Lead Scheduler, Fluor, OTIA III Bridge Program, Eagle Commuter Rail Project, US 183 South Project

START Date: 
June, 2007
END Date: 
October, 2016

US 183 South Project - Austin, TX

Experience Hours (Planning & Scheduling): 
4000
Experience Hours (Cost Management): 
10000
Experience Hours (Forensic Analysis): 
500

Sr. Project Engineer- QS, Billing & Planning, Fusion India Project Management Pvt. Limited., Civil Buildings & Residential Projects.

START Date: 
December, 2014
END Date: 
July, 2015

Position – Sr. Project Engineer- QS, Billing & Planning

 

Presently I was a part of project monitoring and planning group at our Corporate Office and majorly

Involved in

 

Corporate Director of Project Controls, Saulsbury Industries, (various projects) all in US and Canada

START Date: 
January, 1989

Mark Boroff - Director of Project Controls

General Information/Job Summary

Experience Hours (Planning & Scheduling): 
40000
Experience Hours (Cost Management): 
5000
Experience Hours (Forensic Analysis): 
4000

Planning and Project Controls Engineer, Nasser S Al-Hajri Corporation, JERP

START Date: 
February, 2010
END Date: 
February, 2012

·         Created/Updated Project Schedules (Level 3 & 4) using Primavera 6/ MSP

·         Defined WBS and monitored the progress of the same at WBS Levels

·         Assisted in Preparing budget and Predicting Cash Flows

Experience Hours (Planning & Scheduling): 
4000
Experience Hours (Cost Management): 
1500

Senior planner, Babcock Engineering, Various

START Date: 
February, 2002
END Date: 
June, 2007

Engeering planner, creating project schedules in MSP and P3 as well as undertaing project risks analysis with @risk and Primavera risk

Experience Hours (Planning & Scheduling): 
4000
Experience Hours (Cost Management): 
2500
Experience Hours (Forensic Analysis): 
500

Head of PMO, Wien Energie GmbH, Organizational Development

START Date: 
September, 2012

Head of PMO at Wien Energie, responsible for the development of internal project and program management standards. Working as an internal consultant to improve company's project management maturity level with main focus on capital projects in the area of renewable energy, maintenance and technical amendment. Coaching of project management staff, in particualat in resolving project issues, claims, scheduling and cost control.

Establish and maintain company wide project management education and development programs for project managers, project owners and project team members.

Experience Hours (Planning & Scheduling): 
2000
Experience Hours (Cost Management): 
3000
Experience Hours (Forensic Analysis): 
1000

Planning Engineer, IOT Infrastructure and Energy Services, Gauwhati Refinery - Carbon block delayed coker unit costruction

START Date: 
March, 2011
END Date: 
March, 2012

ADeveloping and maintaining detail project schedule

AEngaging team members actively in day to day work by delegating work to appropriate individuals on long term as well as daily basis

AAdhering to recommended execution philosophy in line with CPM and LOB execution basis

AInvesting in the study of project progress trend and suggesting alternative means of achieving targets so as to meet the deadlines and achieve the milestones

Experience Hours (Planning & Scheduling): 
1150
Experience Hours (Cost Management): 
300
Experience Hours (Forensic Analysis): 
600

Sr Planning Manager, APP Corporation, Construction of Grand Hyatt Hotel

START Date: 
November, 2000
END Date: 
September, 2002
Sr Planning Manager. My role involved as CM consultant for Planning, Procurement, Coordination with Client and Contractor, Monitoring, Expediting progress and supervising some part of Construction on a 5 Star Hotel Project
Experience Hours (Planning & Scheduling): 
2850
Experience Hours (Cost Management): 
500
Experience Hours (Forensic Analysis): 
500

Market Place

Primavera P6 and Microsoft Project books, on-line video training courses and training material available from an internationally recognised publisher. Teach yourself using on-line or book based learning or run your own in-house or public courses.
Syndicate content