Leading planner (promoted in 2015), GSI-Giprokauchuk, Certified Project Management Associate (IPMA Level D®)

START Date: 
July, 2013
GSI-Giprokauchuk, (OJSC "GSE")

Moscow, 

Planning field: 1. Responsible for: 
- WBS and CBS development 
- scheduling of project execution deliverables reflecting the designated level of detail for tender-stage schedules and for full-phase contract execution 
- time-sheet information is regularly entered into the project document programme 
2. Coordinate subcontractor’s major milestones and resolve schedule issues. 
3. Man-hours and actual data input of weekly activity status into the Primavera 6.0 system. 
4. Up-dating of schedule progress. 
5. Created ad hoc Project Planning documents and assistance on planning methodology to Contractors counterparts. 
6. Updating the Primavera database (OBS, codes, user defined fields, etc). 

Progress Monitoring and Reporting: 
1. Responsible for: 
- following-up of quantities to be performed in any discipline, analysis of trends on the level 1,2 and 3 schedules 
- weekly reporting of implementing plan vs. actual progress curves, manpower histograms for expenditure forecasting and progress (S-curves, MPS, progress tables) 
2. Critical Path Analysis (CPM), with a focus on early identification of risks to facilitate preventing actions. 
3. Establishing of schedules and recommendation of actions to drive on-time performance with the goal to complete the project on time. 
4. Provide detailed feedback to Production Manager. 

Participation in development of System of control of working hours from point zero - 12 production departments and 5 subsidiaries : 
- description of business processes 
- development of documents of Integrated management system (work instructions, templates) 
- checking of value of contract measured in man-hours based on labor production of designing document 
- annual budget preparation and its verification for each production department 
- database administration (adding users, contracts, etc.). 

Сustomers - LUKOIL, TANEKO, Nizhnekamskneftehim, Tobolsk-Polimer, TOTAL (five current schedules at present).

1)      Complex of oil refineries with a capacity of 14 million tons of oil per year (customer JSC "TANECO")

2)      Transportation system of liquid hydrocarbons from the fields of Bolshekhetskaya cavity (LLC "LUKOIL-Western Siberia")

3)      Project documentation: Delayed coking unit “TANEKO“ in Niznekamskneftehim (Customer:: LUKOIL-Nizegorodniinefteproekt) regulation

4)      Project documentation ("P" and "R" stage): Renovationof the productionof alfa-olefins with productive capacity 37 500 per year (Customer:: JSC "Nizhnekamskneftekhim")

40 000 mh

5)      Kharyaga field development Project, phase 3, EPC (Customer: JSC Globalstroy-Engineering, TOTAL) 

6) Review of project documentation for AHICarrier FZC.