Planning Engineer, Qatargas , Common VOC Project (Phase-I)
START Date:
February, 2008
END Date:
December, 2010
Planning Enginner for Civil/Mechanical/E&I/F&G/Telecom including new Substation work in Reclaimed Land & Loading berth in Common VOC Project (Phase -I) .Client : QATARGAS
- Preparation level IV schedule based on different calendar's id subject to the ship loading window at different jetty
- Engineering/procurement final delivery follow-up based on the construction requirement
- Preparation of "S" curve based on man-hours and Man-hours derived from quantity of work
- Preparation and updating the PPC (Physical progress for construction) based on area & discipline wise.
- Manpower allocation & mobilization
- Monitoring the Field progress
- Review & approval of subcontractor schedule and manpower mobilization & other reports
- Filtered the 3W look ahead and produce to construction team. Generally it is generated from base line schedule with back log.
- Work front identification for subcontractor and monitor the progress based on work front.
- Study and analyze the critical activities & list out the hold point and highlighted to client.
- Preparation & submission of Weekly & monthly construction progress report also reporting to company regarding the main area of concern from Client side & company side.
- Co-ordinate the Construction meeting with subcontractor & subcontractor team