Planning Engineer, Qatargas , Common VOC Project (Phase-I)

START Date: 
February, 2008
END Date: 
December, 2010

 

Planning Enginner for Civil/Mechanical/E&I/F&G/Telecom including new Substation work in Reclaimed Land & Loading berth in Common VOC Project (Phase -I) .Client : QATARGAS

 

  • Preparation level IV schedule based on different calendar's id subject to the ship loading window at different jetty
  • Engineering/procurement final delivery follow-up based on the construction requirement
  • Preparation of "S" curve based on man-hours and Man-hours derived from quantity of work
  • Preparation and updating the PPC (Physical progress for construction) based on area & discipline wise.
  • Manpower allocation & mobilization
  • Monitoring the Field progress
  • Review & approval of subcontractor schedule and manpower mobilization & other reports
  • Filtered the 3W look ahead and produce to construction team. Generally it is generated from base line schedule with back log.
  • Work front identification for subcontractor and monitor the progress based on work front.
  • Study and analyze the critical activities & list out the hold point and highlighted to client.
  • Preparation & submission of Weekly & monthly construction progress report also reporting to company regarding the main area of concern from Client side & company side.
  • Co-ordinate the Construction meeting with subcontractor & subcontractor team