Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

PLANNING ENGINEER

Planning Engineer, Tecnicas Reunidas, Talara Refinery Modernisation

START Date: 
December, 2015
END Date: 
August, 2017
-Develop Work breakdown structures.-Develop Schedule-Collect field data to develop and update project Master Schedule.-Monitor and measure weekly construction progress and performance.-Revise the project plan and project schedule (re‐planning and re‐baselining) as required.-Prepare and provide project progress reports.-Control progress and performance of contractors.-Develop shutdown schedules.-Prepare procedures and guidelines for project planning and scheduling management and control.-Assi
Experience Hours (Planning & Scheduling): 
2200
Experience Hours (Cost Management): 
0
Experience Hours (Forensic Analysis): 
1000

Planning Engineer, Graña y Montero, Las Bambas Copper Concentrator

START Date: 
January, 2013
END Date: 
October, 2015
-Develop Schedule-Develop Work breakdown structures.-Collect field data to develop and update project Master Schedule.-Monitor and measure weekly construction progress and performance.-Revise the project plan and project schedule (re‐planning and re‐baselining) as required.-Control progress and performance of contractors.-Reporting.-Lean Construction.-Forensic Scheduling.-Earned Value.-Budget Control.
Experience Hours (Planning & Scheduling): 
3200
Experience Hours (Cost Management): 
1000
Experience Hours (Forensic Analysis): 
1000

Planning Engineer, Siemans, GREAT MAN MADE RIVER PROJECT

START Date: 
April, 2000
END Date: 
November, 2001

Development of schedules for design and installation of the SCADA remote operating systems for Great Man Made River Phase 2 (the pumping of fresh water from an underground lake through 1,000km of 5m diameter Water Pipe and Pumping Stations between south Libya and Tripoli).

Experience Hours (Planning & Scheduling): 
2750

Planning Engineer, Lothian Regional Council, General Maintenance of Lothian Region Water & Drainage

START Date: 
June, 1992
END Date: 
February, 1995

Provision of the day to day planning for maintenance and emergency repair of the water and drainage services.

Experience Hours (Planning & Scheduling): 
3000

Planning Engineer, BNFL (Sellafield Sites), Enhanced Actinide Removal Plant

START Date: 
February, 1992
END Date: 
March, 1993

Development of schedules, progress updates and reports for the Enhanced Actinide Removal Plant Commissioning. 

Experience Hours (Planning & Scheduling): 
2000

PLANNING ENGINEER, kazstroy services india ltd., Guru Gobind Singh Refinery Project

START Date: 
July, 2008
END Date: 
June, 2010

2008 -2010                    HMEL “Guru Gobind Singh Refinery Project”

  • CDU/VDU, DHDT & NHT/CCR Heaters Works

EPC Project with In- House Engineering and successful completion of heaters with commissioning assistance to the client.

 

Main activities:

 

Experience Hours (Planning & Scheduling): 
3650
Experience Hours (Cost Management): 
600
Experience Hours (Forensic Analysis): 
200

Planning Engineer , NES Pak , IIUI Admin Buildings

START Date: 
January, 2010
END Date: 
January, 2012

Planning Engineer at National Engineering Services Pakistan 

Experience Hours (Planning & Scheduling): 
4000
Experience Hours (Cost Management): 
1500
Experience Hours (Forensic Analysis): 
100

Planning Engineer, INSITE DIMENSIONS INTERIOR DECORATIONS L.L.C, Hotels, Various Shopping Malls & Residential Apartments

START Date: 
October, 2014
END Date: 
March, 2017
  •  Preparing recovery programs to meet the planned Dates for the project.
  • Establishing Progress Measurement Systems within the Project for accurate monitoring of works.
  • Tracking project progress over P6 and reporting to the project manager, clients and consultants.
  • Using Spider Project Professional to create construction programs for the Fit-Out works involved in the project.
  •         Maintaining the material procureme
Experience Hours (Planning & Scheduling): 
3500
Experience Hours (Cost Management): 
500

Planning Engineer, DEPA Interiors LLC , 5- Start Hotels , High End Multi purpose Buildings - Complete Fitout Scope

START Date: 
April, 2017
  • Monitoring and Tracking Site Progress
  • Assisting PMO in Forensic Delay Analysis
  • Implementation of EVM to monitor Project cost progress.
  • Oversee schedules and risk management plans and provide warnings hindering project results.
  • Maintain and validate project schedule information through regular collaboration with project staff.
Experience Hours (Planning & Scheduling): 
4000
Experience Hours (Cost Management): 
1000
Experience Hours (Forensic Analysis): 
3000

Planning Engineer , LEAD Contracting & Trading Limited, Engineering, Procurement and construction EPC Project PI-17038, TINRHERT FIELD DEVELOPMENT, ALGERIA

START Date: 
January, 2019
END Date: 
July, 2020
  1. Develop, review and maintain the project plans and baseline schedules using Primavera
  2. Monitor progress throughout the construction process on a weekly basis and compare with work plan (Actual vs Baseline Schedule)
  3. Identify and review regularly, critical and sub-critical activities and monitor its impact on overall plan
  4. Develop and maintain project change control and review scope change requests for impact on schedules and the critical path of the project.
  5. Submitting planning package with all allied documents
  6. Ensuring availability of drawings in l
Experience Hours (Planning & Scheduling): 
3700
Experience Hours (Cost Management): 
100
Experience Hours (Forensic Analysis): 
50

Market Place

Primavera P6 and Microsoft Project books, on-line video training courses and training material available from an internationally recognised publisher and PMI accredited REP. Teach yourself using on-line or book based learning or run your own in-house or public PMI accredited courses.
Syndicate content