Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

PLANNING ENGINEER

Planning Engineer, Fiatavio Foster Wheeler, Serene no. 8 Cogeneration Power Plants (no. 4 of 100 MW and no. 4 of 50 MW)

START Date: 
April, 1994
END Date: 
June, 1994

Recruited to assist in the programming and scheduling for the development of the Serene project, in which FiatAvio intends to build gas turbine based cogeneration systems to provide electric power and process steam to Fiat facilities located at various sites in Italy, mainly in the South.

Planning Engineer, ABB SAE Sadelmi, 380/132 kV Substation 9009

START Date: 
October, 1995
END Date: 
February, 1996
Responsible for planning and reporting on the 380/132 kV Substation 9009 project, consisting in 30 bays of 380 kV Gas Insulated Switchgear and 14 bays of 132 kV Gas Insulated Switchgear.

Planning Engineer, Turbotecnica, Nuovo Pignone Group, Cogeneration Power Plant CET3 - Electrical power output of about 600 MW

START Date: 
March, 1996
END Date: 
March, 1997
Recruited during the installation phase of the thermoelectric power plant CET3 (no. 3 gas turbines Nuovo Pignone of 115 MW and no. 3 steam turbines Ansaldo Industria of 85 MW) inside the Ilva steel works mill at Taranto. This is an innovative plant: a combined cycle fed by recovery fuel gases, produced by the steel work process, provided with a post-firing system.

Planning Engineer, Turbotecnica, Nuovo Pignone Group, Delimara Power Station Phase IIB

START Date: 
April, 1997
END Date: 
July, 1998

Combined cycle plant of 115 MW comprising two gas turbine generators Nuovo Pignone of 40 MW, a steam turbine General Electric of 35 MW, two heat recovery boilers, electrical high and low voltage systems, transformers and a distributed control system. Including fuel transfer and purification systems, feed water make-up and storage tanks, demineralising plant, sea water screen and pumping system. Responsible for the preparation and maintenance of the project schedule, review and comment on Contractors schedules and progress. Preparation of weekly and monthly progress reports.

Planning Engineer, RELIANCE ENGINEERING ASSOCIATES LTD, Jamnagar Export Refinery Project (JERP)

START Date: 
July, 2005
END Date: 
October, 2007
  •  Prepare and Update Various Registers pertaining to Engineering Deliverables, Procurement services, Manufacturing, Sub Contracting & Construction
  • Recording Progress of all discipline and Updating the schedule developed and monitoring it with the Project Baseline Schedule
  • Report generation on daily, weekly and monthly basis speaking on Achievements, Critical Issues, Schedule Analysis, Progress Analysis, Front Analysis and Resource Analysis
Experience Hours (Planning & Scheduling): 
4500

PLANNING ENGINEER, CNNC China Nuclear Power Engineering Co., Ltd., The Company's Infrastructure Project

START Date: 
September, 2016
END Date: 
April, 2019
Main responsibilities:(1) Being responsible for development and management of plan and cost in the  company's infrastructure projects;Achievements:(1) To ensure that the scope of schedule and cost are under control for the company infrastructure project;(2) Establishing standardized infrastructure project management system;
Experience Hours (Planning & Scheduling): 
5000
Experience Hours (Cost Management): 
2550
Experience Hours (Forensic Analysis): 
2050

Planning Engineer, China Petroleum Engineering & Construction Corporation (CPECC), 1.5 Million Tons/Year Continuous Reforming Unit Construction Project in the CNOOC Ningbo Daxie Petrochemical Company

START Date: 
January, 2015
END Date: 
January, 2016
Main responsibilities:(1) Being independent management of project plan,schedule and progress;(2) Being responsible for the planning of milestones, critical path, special control progress for project control system;(3) Being responsible for development and management of all level schedule ;(4) Being responsible for measurement of the project progress ;(5) Being responsible for monitoring progress by using physica
Experience Hours (Planning & Scheduling): 
2500

Planning Engineer, Tekfen Construction and Installation Co., Yanbu - Jeddah Pipelines Project

START Date: 
February, 2017
END Date: 
September, 2017


Employer: Saudi Aramco
Project Budget: 300,000,000 USD

Project Description: 20”x333.5 km gasoline, 24”x333.5 km diesel & jet A1 pipeline. 8 valve stations, 4 scraper traps, 430 km of fiber optic cable, 19 nos. thrustboring, cathodic protection etc.

Experience Hours (Planning & Scheduling): 
1800

Planning Engineer, Yapi Merkezi, Awash - Kombolcha - Hara Gebaya Railway Project

START Date: 
April, 2015
END Date: 
December, 2016


Employer: Ethiopian Railway Company (ERC)
Project Value: 1,699,900,000 USD

Project Description: 426 km long railway project pertaining to design, manufacture, assembly and operation startup of track superstructure, maintenance facilities, workshop and depot areas, stations, service building, track works, signalization, catenary systems, generator rooms, telecommunication and training of personnel.

Experience Hours (Planning & Scheduling): 
4000

PLANNING ENGINEER, Energy Technical Services, EPIC for Replacement for Fire Water Pumps At Khatiyah %26 Umm Bab in QP Dukhan

START Date: 
December, 2016
END Date: 
July, 2018

•Prepare baseline schedule for project and Update Project Schedule in Primavera P6

• Preparing and update Procurement status register, Construction Status register.

• Prepare change requests and work cost variation if required.

• Cost control and Budgeting

• Coordination with Clients, Subcontractors & Vendors

• Prepare daily, weekly and monthly status reports with S curves phase wise

• Prepare 90 Days Look Ahead Schedule

• Prepare Productivity Reports

• Prepare and Update trend register

Experience Hours (Planning & Scheduling): 
2550
Experience Hours (Cost Management): 
1000
Experience Hours (Forensic Analysis): 
400

Market Place

No results found... (try selecting a different content filter)

Syndicate content