As Built Critical Path

Member for

20 years 11 months

Hi Stephen,



Et Tu



[Clearly, this thread has drunk its last dregs. Please begin another if you wish to continue restating your position. The Moderators]

Member for

20 years 11 months

Bon Jour Stephen,



How about the "Path to Reality",



Regards



Philip



Ps the WI is doing well

Member for

20 years 7 months

How about:



The One True Path!

Member for

20 years 11 months

Hi andrew,



Iwould agree with something like delay causing activities, or retrospectivive analisis of problomatical activities, call it what you will.



Regards



Philip

Member for

20 years 10 months

New name for ABCP - as built sequence of critcal activities



Any takers??????????????????

Member for

20 years 10 months

Phillip,



Would you agree with, that which it completed cannot be critical anymore, but also that which is completed may have been critical at the time of it’s construction?

Member for

20 years 11 months

Hi guys,



I think I have always stated that which is completed cannot be critical anymore.



The point I see coming out of this is hihdsight is perfect vision. Maybe we should try some more foresight as planners, and leave the hindsight to the planning pathologists.



By the way Stephen, SA should win this one, but not tway I would have liked it. With all the WI top players on a strike, it will not be the ideal reflection.



Regards,



Philip

Member for

22 years 8 months

Hi Philip,



The planner may not have been right, some of the records may not be accurate, but what is the likelihood of all of the records being incorrect? True there will be contradictions and inconsistencies in the records, nobody said it would be easy. The job of the analyst/expert witness is to research all of these elements and interview as many of the project team as possible, including the project planner. It can be a massive and time consuming task, as Gary said he was involved in Great Eastern for a year, this is not unusual.



The whole point of retrospective delay analysis is that this is a post mortem of the project. The forensic analyst researches/investigates what WAS critical to the problem.



Having read several of your posts, I think there is a slight problem with your thinking, in that when you write you do so in the future tense "is completed CAN be critical". In retrospective analysis it is about what WAS critical, like your example of the illness in a corpse, the illness WAS critical to the death of the corpse.



DW

Member for

22 years 9 months

Slightly off topic ... assuming an ABCP is a reality - how does one go about finding it retrospectively; or perhaps more simply how does one etablish EOT entitlement retrospectively.



Not suggesting this be answered in this thread, so have started a new one.



Your thoughts would be very welcome - the new thread is entitled "Delay Analysis Methods"

Member for

22 years 9 months

Philip



Your sentiments are well voiced and received - but remember, you’re writing them in a forum entitled "Contracts, Claims & Claims Assessment". While no one can criticise your idealism I think you ignore reality - i.e. that it is (alas) often very very relevant to determine historically what was critical on a project at a prior point in time.



Clients, Courts and Tribunals are constantly looking for assistance from experienced project planners on this subject - surely you can’t be suggesting they are seeking answers to an impossible question?



A Happy New Year to you and all the other forum participants also.



David

Member for

20 years 11 months

Hi Guys,



Hope you all had a pleasant XMas, and all my best wishes for 2005.



What is the point of planning, how to work out the best way to carry out a project, and then to monitor it as the work progresses. Therefore, planning is all about the future, and what is past is history.



The reasons for analysing an as-built schedule may vary from project to project. This depends on the purpose of the analysis, ie whether it is for a claim,improving future planning or even to see why the planning was successful or a disaster, etc.



The point I stiil make is that history is in the past and cannot therefore be critical. The events that happened might have had a serious impact on the future, and even if they were critical at the time, cannot be changed. I think the point of history is analysing the mistakes/positive achievements and using this information to improve the future.



So instead of discussing this so-called enigmatic "AS-built critical path", let’s rather discuss more beneficial ways of using as-built schedules, to improve future planning.



Regards



Philip J

Member for

22 years 9 months

Gerry et al



Being an "As-built critical path ’o-phile" I’ve found the thread interesting.



It seems to me that the answer has to be yes - it exists!

Subject to the information being available a skilled planning analyst can surely advise what was critical at any point in time on the project. If we also believe the critical path can switch, then surely connecting all the retrospectively determined critical activities together results in (yes wait for it ...) the "as-built critical path".



Of course you could all just be talking about the ability to locate the as-built critical path via programming software (i.e. via a logic linked dynamic as-built programme) then I would say it is possible in threory - its just not reliable!



Gerry - get back to work!



Regards

David



If we can say in retrospect what was critical at any point in time (using analysis) then

Member for

24 years 4 months

Jaco,



Your example with the 2 Iso’s.



You do not say if the float on the 2 Iso’s is the float on the original as-planned programme or what was available at the time of issue of the Iso’s.



A claim, for eot or delay, that is based on the float as shown on the as-planned programme only would not succeed.



It it is the float at the time the the Iso’s were issued, then the contractor is entitled to a 5 day eot for late issue of Iso 1. Most contracts encourage an extension of time to be awarded when the completion date is "likely" to be delayed, i.e. at the time of the delaying event.



At the end of the project, to establish actual delay caused by either Iso 1 and/or 2, then further investigation and substatiation is required to support a ’loss & expense’ claim, and not just an as-built programme or as-built critical path.



Sorry, I have digressed from the thread, but this is important. An as-built critical path, or any cpm delay analysis, is there to support or compliment a delay claim; but the delay claim must be based on facts.



Roger Gibson

Member for

24 years 8 months

Jaco



What you state goes to the heart of some extremely difficult questions in delay analysis.



Have you read the SCL protocol - see www.eotprotocol.com.



I put my view on records and the SCL were kind enough to put my paper on their web site.



Gerry.




Member for

21 years 1 month

I am still a Believer in an as Build Critical Path.



Example (Piping)



Two Different Iso.



Iso one

Release Dwg (Activity Critical) (Late 5 Day’s)

Construction Planned 14 Days Actual 7 Days



Iso Two

Release Dwg (Non Critical 10 Days Float) (Late 8 Days NO EOT)

Construction Planned 14 Days Actual 24 Days



Project Delayd 5 Days as per Projected CP (Real Impact none)

Project is Delayed Actualy by 8 Days (Please note non Critical Activity)



The only way how you can see this is after the project is completed. Then you would be able to see that ISO two was the real Critical activity and ISO 1 was not ???.



I know you can argue that the activity become critical but you don’t know the full impact before it is completed.



Cheers




Member for

24 years 8 months

Stuart, many thanks for lifting the quality of debate - it was waning.

Member for

21 years 4 months

Vladimir,

I was expressing the view that I can understand how the CP can be applied to the future: I was not being categorical or dogmatic about the issue.

I was stating that I am persuaded by the view that a CP can only apply to the future; I was not defining it. Nor have I been persuaded by earlier parts of this thread – within a strict planning and scheduling context – that a CP exists retrospectively.



That is not to say, of course, that I don’t use the term when presenting a delay claim predicated on historical events that have had an impact on the CP at that time.



Cheers,



Stuart



www.rosmartin.com

Member for

24 years 8 months

Dear Stuart,

please advise me where in the definition of the Critical Path I may find that "a "Critical path" can only apply to the future".

Thank you in advance,

Vladimir

Member for

21 years 4 months

PHEW!!! – and I used to get complaints about some of my long threads and wanderings!

I’ve now had a chance to catch up, so let me throw my hat into the ring!!



Having just completed planning an other piss-up in a distillery, I can see this in a different light!

I think that it all depends on which hat you are wearing!



I believe that Martyn and others may be correct in saying that by definition the terms "As built" and "Critical Path" cannot be used together, since an "As built" schedule is one that has been updated with actual starts and finishes, whilst a "Critical path" can only apply to the future. And I am persuaded by this view from a strict planning perspective.



But as Gary also correctly points out, when you are trying to explain the historical events that impacted a Contractor’s performance (in lay terms and often to a lawyer or a sleepy Judge!), the term “As-built Critical Path” is used to describe such causes and effects. The “As-built Critical Path” is a term used (or abused!) to describe the sequence of actual events that happened throughout the execution of the project and which, as a result of their occurrence, had an impact on the Critical Path at that time.



So I think that from a strict or clinical planning perspective, many of you are right in that an “As-built Critical Path” is a contradiction in terms and cannot exist, but from a delay claims perspective, it is a term frequently used to describe the historical events that impacted a critical path in pursuit of a claim for delay.



Does this clarify or confuse? ;-)



Stuart



www.rosmartin.com

Member for

21 years 11 months

Hi Philip,



Thanks for your question.



The planner on the project was not right, although generally he recorded the progress position reasonably well, which the two planning experts (one for the defendant, one for the claimant) agreed to use as being mainly factual. However, the two of the big issues that had to be faced during the trial were that the project planner did occasionally record the progress incorrectly and this was discovered by photographic evidence and secondly he made changes to the logic of the programme which did not make sense. These logic changes did however alter the critical path of the programme at the time and gave incorrect completion date forecasts / progress reports on a number of occasions. This was not picked up during the project itself, only afterwards by the post-mortem planners. Progress photographs are really wonderful things in disputes. Regarding dairies, minutes, correspondence and reports, these were all examined as part of my work. As you can imagine, on a complex project such as GEH, the amount of documentation to go through was enormous.



On your second point, this is what is often called the concurrency issue. The big question here is what impact, if any, did these different secondary critical paths have. That was also a significant issue at the trial. Lets just say that these secondary, or concurrent, critical paths were also examined in a great deal of detail for the trial and it was crucial that the post-mortem planners look at these as well, which we did. The project planner (and the defendant) claimed these had an impact on the project, but the judge did not agree.



Concurrent critical paths is probably worthy of a new thread.



Regards,



Gary France

Member for

22 years 3 months

Gerry, I have already been given my opinion at the start of thread and no change in the statement so far.

Member for

24 years 8 months

Shahzad, what’s your conclusion? Does an as-built critical path exist?



Gerry.

Member for

22 years 3 months

The simple issue has been so pronloged and discussed to understand the word " As built". I think enough and valuable discussion should come into conclusion now.

Member for

22 years 9 months

Jaco,



It is an interesting idea, but you cannot calculate a longest path using actual durations. – Let me put this another way, such a calculation without modifications would be meaningless.



A longest path calculation using just actual durations would ignore that fact that many activities begin before they are logically able to do so. This fact, in part accounts for the increased durations commonly found. In addition to using actual durations, you also need to adjust the logic to account for the actual early starts.



I have been thinking of this issue for a long time. In fact, I have written software called As-Planned/As-Built Maker that creates such a schedule from the As-Built schedule. You can read more on this at http://www.ronwinterconsulting.com/forensic_brochure.htm.



As for relying on what computers ’say’ is correct - first you need to at least know what they are saying. That is why the As-Built Critical Path is so important.

Member for

21 years 1 month

Hi Ronald



Maybe the word Right was not correct BUT the computer program (Example P3) is told to calculate the the Longest Path on Remaining Duration. If you program P3 to Calculate on the Actual Duration it will also give you the "As Build CP"



Have you ever had a case were the schedule tells u this is your CP and you know it is wrong then when you check the logic you find the mistake. We must not rely on Computers and belive everything they "Say" is correct.



As far as Politicians go " I have heard politicians say "I have never had ... with this woman" But then again it depends what you define "...." as. So my conclusion are they always tells the "truth" from their perspective.



Cheers


Member for

22 years 9 months

Jaco,



You need to better define the word, ’right.’ Do you mean ’accurate’ or do you mean ’truth.’ A computer program will not give you truth (neither will a politician.)



A computer program can tell you what the schedule says is the As-Built Critical Path. But then again, isn’t it important to know what the schedule says? Is this not the first step? Without this, everything else is just opinion.



The truth may be something different. I prefer to testify as to what the schedule says is the critical path. This (at least) can be proven.

Member for

21 years 1 month

Gerry



Here is a Thought



The Critical Path can only exist in an As Build State.



The Reason

As so many NON Believers have agreed is that the critical path keeps on changing. So if you say something is Critical now it does not mean it is stil critical in a second/Minute/Hour/Day/Week/month from now.



So to see the true Critical Path you can only see it when you have completed the project. (Not before because it is your "current" projected critical path) (Remember a critical path the longest path)



Cheers

Member for

21 years 1 month

Uri

Remember a computer program is not always right. Just because it tell you does not mean it is right.

Member for

24 years 8 months

Uri,

critical path is by definition the longest path in the network. If I will want to learn what path in my network is or was critical (i.e. longest) I need to look not only in the future but also in the past.

If at the start of the project all activities in my schedule are ALAP then all of them are critical (have zero floats) but still there is a critical path, isn’t it?

Vladimir

Member for

22 years 5 months

Vladimir,



You said the Critical path does not necessarily refers to the future. Just look for a moment at one of your programmes:



Are there any Critical activities to the left of the data date? (in the past)



Is there any float to activities in the past?

Member for

20 years 7 months

Philip wrote:



". . .it is something like an post mortem, how can you find an ilness in a corpse, that is critical, you can only analise what the problem was and try and prevent in the future."



But, Philip, isn’t that the point? And as Vladimir suggested, isn’t that a very important thing to do? (Along with assessing past responsibility and competence, of course!)



As to the name ABCP, personally I’ve always hated the term "total float" ascribed as an attribute of an activity. "Float" is fine; the "total" (even if followed by "slack"!) is just confusing, as the activities’ respective float is not "totalled" along a path.



However, the term has been in project management a lot longer than I have, so I’d better understand what it means when people use it (as they will!). Personally, I kind of like the term "actual critical path". But I don’t think this would allay your concrns. . .



BTW, Phil, I don’t know if you’re a cricket fan, but if you are, I may enjoy tweaking you a bit when West Indies start beating South Africa in a few days. . . (Just joking! South Africa should win.)


Member for

24 years 8 months

Gary,



Do you use your as-built-critical-paths to undertake substantive collapsed as-built analysis?



Gerry.

Member for

21 years 11 months

Martyn,



I am afraid I cannot agree with you. I have drawn many as-built critical path programmes as part of delay analysis expert witness work. An as-built programme is simple to understand - as you correctly say, it is simply a programme that has been updated retrospectively with actual start and finish dates to demonstrate when each activity actually took place.



To this one can add the actual logic that dictated when each activity took place. By rescheduling the programme, one can demonstrate the as-built critical path. In other words, the longest chain, or chains, of activities through the programme that cause the completion date to be when it was.



This addition of actual logic has to be done very carefully and it certainly demands a considerable amount of close scrutiny to ensure the correct actual logic is used.



In my opinion the use of as-built critical path programmes is not at all uncommon.





Gary France

Chairman

The Planning Engineers Organisation

Member for

22 years 5 months

I really am at pains to understand why this has been such long ongoing thread. By definition the terms "As built" and "Critical Path" cannot be used together. An "As built" scheduled is one that has been updated with actual starts and finishes, a "Critical path" can only apply to the future. An "As built" can only influence the "Critical path" if the actual dates were later than predicted it would then impact the future dependant activities that have not started, possibly creating a "Critical Path".

Member for

24 years 8 months

Gerry,

you described the method of its calculation. I quoted the definition. If some method does not work it does not mean that the problem does not exist.

Vladimir

Member for

24 years 8 months

Vladimir



Critical Path is reliant upon a forward pass and a backward pass in order to determine earliest and latest dates for the activities. Where to actual dates (i.e. in the past) fit in? In the past there is no earliest or latest dates, there are only actual dates. That is Philp’s point.



Gerry.








Member for

24 years 8 months

Critical Path is defined as the longest path in the net. That’s all. Nothing about future or past.

Vladimir

Member for

20 years 11 months

Vladimir,



Explain that one please, about the future?



As I have said before, how can something in the past be critical. Therefore only things in the future have the risk of becoming critical.



Regards



Philip

Member for

24 years 8 months

There is nothing about the future in the critical path definition.

Member for

20 years 11 months

Hi Gerry and all other contributors,



It’s been an interesting one. Thanks all.



An interesting question to PPAdmin what has been the longest thread to date on the site?



Regards



Philip J

Member for

24 years 5 months

Uri,



That’s what I mean, when As-built is combined with the term Critical path it becomes confusing. People tend to interpret it in many ways.



Se

Member for

20 years 11 months

Hi Gary,



So you did the post mortem, but what if the planner was not right, how did you find the correct history, this must mean you gleaned it from daily diaries, minutes of meetings, correspondence, etc, who says this info was all correct? I stated a little earlier, that the quality of the planning is important, that is, recording the facts.

What if the delays happened in different areas, and as result, in different logical paths, and started compounding the isuue?



Regards,



Philip

Member for

22 years 5 months

Sigfredo,



I agree with you that there is a problem, however to me the problem is not with the term As-built Programme. This term is commonly used and self explainatory.



The problem lies in the combination of As Built with Critical Path, as usually Critical Path relates to the FUTURE and As Built relates to the PAST.



My personnal opinion is that there is no such beast as ’As Built Critical Path’

Member for

24 years 5 months

"As-Built Critical Path", is it the most appropriate term to use? Can’t we find a suitable term that every time you read it, everyone knows what it means and it doesn’t need clarifications/qualifications when being used. I guess this is one of the reasons why this thread come a long way.



Personally, I find As-built word as confusing as I will immediately compare it with as-built plans. what do you think guys?



Se

Member for

24 years 8 months

Philip(s)



I think your suggested phraseology for the question is just a wee bit loaded and it might just betray your answer!



Thanks for your input, it has been a good thread.



Gerry.


Member for

20 years 11 months

Hi Gerry,



How about the question, "Is there merit/purpose in finding this so-called (mystical) AS-BUILT Critical Path?"



Sorry it took me a while to come back, Update Day here:-)



Regards,



Philip J

Member for

20 years 11 months

Gerry

Sorry - I should have made it clear I knew who you were talking to. I just meant to put in my 3-ha’pence-worth!



We are only too weel aware here abpit the EOT issues. Unfortuanately, many of those invloved 9especially rhe lawyers) do not really appreciate thes issues. I think we ought to make a distinction between an as-built schedule (actual dates) that happens to built on a CPM program and a CP schedule (one where the logic is key).


Member for

24 years 8 months

Sorry Philip Rawlings, my question was directed to Philip Jonker.



As for its purpose (ABCP) - Billions of pounds/dollars are fought over every year in Extension of Time Claims and the notion of an As-Built-Critical-Path is central to many of these disputes.



Just look at the first three quarters of this thread to flush out the views that Planners hold.

Member for

20 years 11 months

Maybe the only useful question is:



Is there any purpose in looking for an as-built critical path?