Plant Operator-Utilities/Pumping & Shipping, CALTEX (Philippines) Refinery, Philippines , Various in-house projects, operation's productivity program, production planning and scheduling

START Date: 
July, 1979
END Date: 
June, 1981
My functions includes the following: Obtain accurate process reading, determine stock transfers and shipments, perform product inventory, blend products, operate the TEL plant, periodic sampling and operation of plant equipment, safety inspection, switching, transferring, feeding in of petroleum products and derivatives to different process unit, equipment maintenance, shutdown, start ups, o
Experience Hours (Planning & Scheduling): 
2550
Experience Hours (Cost Management): 
800
Experience Hours (Forensic Analysis): 
600

Staff Engineer , Coconut Chemicals Inc. (Cocochem)-Philippines , Ballestra Sulfonation Pilot Plant, Commissioning and Start Up program, CMMS development and implementation

START Date: 
July, 1985
END Date: 
October, 1990
Maintenance planning and scheduling during my first year and as a Vibration Technician/Analyst in my second year under the T & I Support Group, Abu Ali Producing and Maintenance Division of ARAMCO, material estimating, support the development of the field's preventive maintenance program, help document various engineering work packages, tag construction work packages; request, receive, c
Experience Hours (Planning & Scheduling): 
4350
Experience Hours (Cost Management): 
1350
Experience Hours (Forensic Analysis): 
1000

Maintenance Planner III concurrently Vibration Analyst Technician I, Arabian American Oil Co. (ARAMCO)-Saudi Arabia, various ARAMCO projects, Maintenance of Operating Plants, Abu Ali, SAFANIYA

START Date: 
November, 1988
END Date: 
October, 1990
Maintenance planning and scheduling during my first year and as a Vibration Technician/Analyst in my second year under the T & I Support Group, Abu Ali Producing and Maintenance Division of ARAMCO, material estimating, support the development of the field's preventive maintenance program, help document various engineering work packages, tag construction work packages; request, receive, c
Experience Hours (Planning & Scheduling): 
2550
Experience Hours (Cost Management): 
800
Experience Hours (Forensic Analysis): 
600

Staff Engineer-Supervisor, Central Azucarera de Tarlac, Philippines, Root Cause Analysis program, Maintenance Program, Predictive Analysis Maintenance Project

START Date: 
April, 1991
END Date: 
July, 1991
My function includes in-house project management, development of standards, process and procedural review, performs mechanical design and engineering feasibility studies, planning and scheduling of all maintenance activities, help establish the preventive maintenance program, supervise the proper execution of all preventive and predictive maintenance program, provide design and engineering
Experience Hours (Planning & Scheduling): 
400
Experience Hours (Cost Management): 
100
Experience Hours (Forensic Analysis): 
100

Professional Mechanical Engineer , Self-employed (PME Part-time Professional Private Practice), Analog Digital Project, various reviews of Mechanical Designs

START Date: 
January, 1995
END Date: 
October, 2001
Delivered engineering/technical services to various clients. Services include the review, checking, verifying and approving of mechanical designs, as-built plans, plot plans and other documents, project site inspections, stamping of IFC drawings and serve as the resident Professional Mechanical Engineer of JG Summit Petrochemical Corporation in 1999 up to 2001.
Experience Hours (Planning & Scheduling): 
700
Experience Hours (Cost Management): 
850
Experience Hours (Forensic Analysis): 
200

Planner/Scheduler, SNC Lavalin, Various mining and metallurgy projects

START Date: 
March, 2011
END Date: 
January, 2016
Functions:Project PlanningScheduling (Engineering, Advanced Primavera P6)Earned Value Analysis (Engineering, Procurement, Construction)Workforce Analysis and ForecastingProject Controls AnalysisProposals Scheduling and Manpower ForecastingResource Loading • Conducted duties with highest regard to Ethical and Safety Standards.• Performed Project Performance Analysis, Ea
Experience Hours (Planning & Scheduling): 
7000
Experience Hours (Cost Management): 
2000
Experience Hours (Forensic Analysis): 
1250

Planning Engineer, Besix, Various roads and infrastructure projects

START Date: 
March, 2004
END Date: 
September, 2006
Projects: Widening of Al Garhoud Bridge, Dubai, UAE ($140M); Ras Al Khor Bridge Crossing, Dubai, UAE, ($50M); Burj Dubai/Khalifa ($876M); Palm Island Access Roads Interchange, Dubai, UAE ($49M); Palm Island Gateway Bridges, Dubai, UAE, ($19M) • Established Primavera P3 project schedules with around 10,000 activities and 6,000 workers based on approved Work Breakdown Structures, constraints and milestones. • Coordinated with Clie
Experience Hours (Planning & Scheduling): 
5000
Experience Hours (Cost Management): 
1000
Experience Hours (Forensic Analysis): 
500

Planning Engineer, Pureworld Middle East - Abu Dhabi, Inter Refinery Pipeline – II Client:TAKREER, Oily Water Sump Project - Habshan Facilities - Client:GASCO, Construction of Cathodic Protection of Well Casing - Client: ADCO

START Date: 
July, 2011
END Date: 
November, 2013
• Preparation of Planning Package as per agreed Schedule and WBS Structure.• S Curve Preparation.• Preparation of Effective Project Progress Monitoring System.• Weekly, Monthly and Daily Report Preparation for Client and Management.• Review of Project Progress with Project Construction Team so as to notify of any deviation and corrective actionpreparation.• Project Budget and Cash Flow Preparation.• Project Cost Control and Reporting.• Subcontractor Administrat
Experience Hours (Planning & Scheduling): 
6700
Experience Hours (Cost Management): 
1900
Experience Hours (Forensic Analysis): 
850

Project Manager, Synthotech Ltd, Synthotech Product Portfolio

START Date: 
October, 2014

Enployed as a Project Manager and responsible for the portfolio of products in development for the gas industry. The projects vary in complexity and time frames. With projects ranging in duration from 3 months to 3 years. I have overall budget responsibility in conjuction with the Innovations Director.

The company has grown from 20 to 50 people in the last year and flexible project managment processes and practices have been implemented as the company's business practices mature.

Experience Hours (Planning & Scheduling): 
1400
Experience Hours (Cost Management): 
500
Experience Hours (Forensic Analysis): 
350

Principal Project Controller, AECOM, Power Supply Upgrade Project

START Date: 
April, 2014
END Date: 
April, 2016

Principal Project Controller at AECOM and working across multiple infrastructure projects.

Experience Hours (Planning & Scheduling): 
2000
Experience Hours (Cost Management): 
1000
Experience Hours (Forensic Analysis): 
1000

Market Place

Primavera P6 and Microsoft Project books, on-line video training courses and training material available from an internationally recognised publisher. Teach yourself using on-line or book based learning or run your own in-house or public courses.