Oil Refinery

Planning & Scheduling Engineer, CTCI Corportion, Oil refinery

START Date: 
February, 2021
-Schedule control of oil refinery project -Work Breakdown Structure (WBS) -Primavera training

Lead Planning Engineer, Technicas Reunidas Sa, Oil Refinery

START Date: 
March, 2012
END Date: 
September, 2014

Tecnicas Reunidas ( Korfez / TURKEY ) ( www.tecnicasreunidas.es )        Consultant : BV                  Project Value : 2.3 B. $

 

Experience Hours (Planning & Scheduling): 
5000
Experience Hours (Cost Management): 
5000
Experience Hours (Forensic Analysis): 
5000

Planning Manager, WorleyParsons, Oil Refinery

START Date: 
April, 2012

 

  • Organization: WorleyParsonsis one of the top EPC organizations in Canada and the world. It was ranked by the ENR magazine as #1 International Design Firm in the world on 2011.

 

  • Project:North West RedWater Sturgeon Refinery - Utilities & Pipe Racks Project.  Providing FEED Phase services including L3 EPC Detailed Schedule, based in Calgary, AB office.

Planning Manager, WorleyParsons, Oil Refinery

START Date: 
April, 2012

 

  • Organization: WorleyParsonsis one of the top EPC organizations in Canada and the world. It was ranked by the ENR magazine as #1 International Design Firm in the world on 2011.

 

  • Project:North West RedWater Sturgeon Refinery - Utilities & Pipe Racks Project.  Providing FEED Phase services including L3 EPC Detailed Schedule, based in Calgary, AB office.

Intermediate or Senior Planner, Makati Development Corporation, OIL REFINERY, -12 High Ends Residential/Condominiums Building Project

START Date: 
July, 2009

PLANNING - Initiates planning for Project Execution including preparations and presentations which includes overall detailed scheduling using primavera 6, formworks, concreting, & procurement schedule, breakdown of resources from approved BOQ then loads to resources in primavera, generates S-Curve, and other data formats which involves schedule and cost of the project as required by the Execution Team and Client.

Sr.Planning Engineer, Mobty, Oil Refinery

START Date: 
January, 2010
END Date: 
January, 2012

Sr.Planning Engineer at Mobty and controlling more than 14 projects 