Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

5* Hotel Project

Senior Planner / Senior Planning Engineer, Arabtec Construction LLC, 5* Hotel Project, Automotive Facility

START Date: 
January, 2014

W     Project site based planning and controlling of projects from contract award to completion. Preparing Project Master Schedule / FIDIC Clause 14 programme - Fully quantified and labour resourced using planning software Primavera 6.8.

W     Programme updates and analysing variances, productivity, bottlenecks, and highlighting to Project Manager.

Experience Hours (Planning & Scheduling): 
3600
Experience Hours (Cost Management): 
500
Experience Hours (Forensic Analysis): 
500

Head of Planning and Project Control, Abadgaran co., 5* Hotel Project

START Date: 
April, 2011

-Preparing and collecting technical data to make reports to the project Management and other Departments (Daily, weekly, Monthly, Annual, Management)

-Providing databases for construction activities, Material delivery, Financial, Man Power, Machinery, Delays 

-Providing and Presenting analyzing reports such as Cash Flow, Procurement Plan, Progress variance and it`s suggestive solution and Cost controlling and earned value analyzing.

-Controlling and analyzing subcontractors financial issues such as invoices and reporting them to the project Management

CONSTRUCTION MANAGER, Space Ace Pvt. Ltd., 5* Hotel Project

START Date: 
November, 2004

ØDischarge of duties for monitoring of projects in line with training manual

 

ØMonitoring day-to-day site activities and guiding all Project Engineers

 

ØOrganising PRM AND DRM, and circulating the Agenda and MOMs

 

ØOverall incharge of construction process monitoring

 

ØMonitoring all intended tests at Laboratory and witnessing the same.

 

Civil Planning Engineer, al daajan, 5* Hotel Project, college buiding, farm house, mall, Office Building

START Date: 
December, 2012
END Date: 
March, 2013

 

EMPLOYMENT RECORD:

                   Now working in AL Daajan construction as same planning engg position as shown below

Previously working in MARG LTD- Chennai   as an Engineer- Planning & Billing  under EPC vertical.

Project Control Manager, Saudi Oger Ltd., 5* Hotel Project

START Date: 
October, 2011

- Currently working as a project control Manager in Saudi Oger in KSA.

- Previously worked with:

* Mubadala ( client ) in Abu Dhabi - from 2007 till July 2011.

* Kharafi National in Egypt and Kuwait ( MEP contractor) from 2004-2007.

* Siemens ( MEP contractor) in Egypt from 2002-2004.

* SIAC contracting company in Egypt from 1999-2002.

* Design career from 1991-1999