Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Site Planning Engineer

Site Planning Engineer, MALAYSIA MARINE & HEAVY ENGINEERING SDN BHD, Gumusut Kakap Offshore Platform Development

START Date: 
June, 2007
END Date: 
May, 2008

1. Prepared and updated workpack and jobcard for Fabrication of Gumusut Kakap Floating Production System

2. Monitored and maintained benchmarking for each fabrication discpline

Experience Hours (Planning & Scheduling): 
2000

Site Planning Engineer, SBM Offshore, Aseng FPSO Project

START Date: 
June, 2010
END Date: 
January, 2011

1. Integrated Project Master Progress Monitoring

2. Maintained and updated integrated activity planning

3. Supervised contractor reporting, progress and performance

4. Prepared weekly and monthly report to Higher Management 

Experience Hours (Planning & Scheduling): 
1300

Site Planning Engineer, Atkins Faithful & Gould, New King Abdulaziz International Airport Development Project

START Date: 
August, 2011
END Date: 
May, 2015

·        Preparation of a comprehensive cost and resource loaded contract baseline time schedule for the Aprons, Taxiways, Load Centers, Airside Storm water network (Pipe and box culverts), Blue Water Network, Airfield Ground Lighting network and the associated Vault Rooms, Glycol Network, 400Hz Network, Fuel Hydrant Network from the Fuel Farm, Fuel supply network from Aramco depot, GSE Tunnel/Ramps and security checkpoints, by reading the design drawings (70%).

SITE PLANNING ENGINEER, GCN, A28 - Viana/Caminha

START Date: 
September, 2003
END Date: 
October, 2005
INDUSTRY: Civil Engineering - Construction and Public Works PROFILE: CASAIS SA, Eusebios SA, Gabriel Couto SA and Aurelio Martins Sobreiro Joint-Venture ROLE: Construction Manager deputy with Planning, QSA and Quantity Surveying responsibilities #PROJECT# - EUROSCUT HIGHWAYS -A28 - Viana do Castelo/Caminha -. 58 Million EUR Construction of 10Km of mountain highway, with 3 viaducts, 2 underpasses, access roads, drainage and electrical infrastructures and slope stabilization . Leaded the QSA and Quantity Surveying departments, with 5 techniques .
Experience Hours (Planning & Scheduling): 
250
Experience Hours (Cost Management): 
750

Site Planning Engineer, DSD Ferrometalco, 2x350 MW Thermal Power Project, 2x650 MW Thermal Power Project, Ammonia Nitrate Plant

START Date: 
October, 2009

Ø  July  2012 till now     ( Planning  Engineer )

Project:EHC-LDAN Ammonia Nitrate Plant

Company:  DSD FERROMETALCO                  Client: HASSAN ALLAM Construction (HAC)

Site Planning Engineer, DSD Ferrometalco, 2x350 MW Thermal Power Project, 2x650 MW Thermal Power Project, Ammonia Nitrate Plant

START Date: 
October, 2009

Ø  July  2012 till now     ( Planning  Engineer )

Project:EHC-LDAN Ammonia Nitrate Plant

Company:  DSD FERROMETALCO                  Client: HASSAN ALLAM Construction (HAC)

Site Planning Engineer, TATA Projects Limited, 4x500 MW ESP Package, 2x300 MW Thermal Power Plant,

START Date: 
June, 2003
END Date: 
February, 2007

Responsible for construction planning of various packages, exception reporting, monthly progress report, etc

Site Planning Engineer, National Grid - Electricity East Alliance , National Grid - Refurbishment Norton Spennymoor 400kv and New Line Tees Crossing

START Date: 
January, 2011

·         Develop, optimise, and agree assigned project  programmes covering the construction aspect of the programme , including milestone definition/achievement, resource planning, cost control  and outage planning, to deliver the work with Asset Management, Network Operations, the Construction Programme Manager, Delivery Manager, Development Manager and Design Manager.

 

Site Planning Engineer, ITD CEMENTATION INDIA LTD., DAM,Canals, Bridges, Aqueducts and Road Project

START Date: 
February, 2006
END Date: 
October, 2006
  1. Activity wise planning and scheduling for the project using Primavera.
  2. Activity wise monitoring and preparation of Impact schedule programme using Primavera.
  3. Attending meetings with Client and co-ordinate the information to other departments.
  4. Progress monitoring and reporting to H.O with MIS formats.
  5. Finding out actual cycle time for major activities in the project.
  6. Taking photographs of all activities at site for Monthly progress Report for Client.

Site Planning Engineer, Ansaldo Energia spa, 5th GT/ WHRB at G Station & addition of BP ST’s at Jebel Ali E & G Stations

START Date: 
July, 1994
END Date: 
July, 1997

Site planning & scheduling using Artemis 7000 andPrimavera Project Planner;

weekly work scheduling/ look-aheads;

preparation of monthly & weekly reports;

project control planning updation;

productivity evaluations and efficiency calculations;

verifying the works with contractual specifications;

verifying completion of each activity with reference to the time constraints;

co-ordinations with sub contractors;

attending meetings with sub contractors, consultant & client regarding the progress;

Market Place

Primavera P6 and Microsoft Project books, on-line video training courses and training material available from an internationally recognised publisher. Teach yourself using on-line or book based learning or run your own in-house or public courses.
Syndicate content