PROJECT CONTROL , Graña y Montero, EXPANDING PRODUCTION CAPACITY - CEMENT PLANT - LIMA

START Date: 
December, 2011
END Date: 
May, 2013

Duties:

·         Preparation of Project deliverables schedule.

·         Update weekly schedule (% complete and update forecast dates).

·         Development of Lookahead and constraints analysis.

·         Control of work ( Earned Value and actual) for developing Curves of progress and construction forecast).

Experience Hours (Planning & Scheduling): 
2650
Experience Hours (Cost Management): 
1950
Experience Hours (Forensic Analysis): 
250