Project Planner, Corvallis S.p.A., Implementation of a Planning Model

START Date: 
May, 2013
Junior Planner. Project Planning and Controlling Activity, consulting for the implementation of Project Managementsystems. Followed Projects:
  • ABB S.p.A. – Preparation of a proposal plan, including progress S curve and man-power histogram, for a tender aimed at designing an offshore plant.
  • ADR Aeroporti di Roma – Implementation Project of the Primavera P6 PPM solution for operational planning and control of the investment process of ADR SpA. Definition of the planning and monitoring procedures. Coaching for Project Planners for the activities of operational planning, physical progress recording and monitoring, variance analysis, issues and risks management.
  • Tecnimont – Implementation Project of the Primavera P6 PPM solution for resource planning and analysis and for cost controls. Definition of the control and monitoring procedures.
  • MBDA Missile Systems – Upgrade and revision project of the planning and project controlling model on the platform "Primavera P6R8.3". Coaching for Project Controllers for the activities of planning, physical progress recording and monitoring, earned value analysis, document management, issues management. 
  • Rosetti Marino – Implementation Prject for an enterprise solution for planning and workload management.
  • Tecnis S.p.A. – Drafting of two time schedules in MS Project for the participation to a tender for the construction of a rail link in Turin, Italy.
Experience Hours (Planning & Scheduling): 
1000
Experience Hours (Cost Management): 
200
Experience Hours (Forensic Analysis): 
300