Planner/ Scheduler, Descon Engineering Qatar, Onshore Gas Project

START Date: 
March, 2012
  • Development and Monitoring of L4 Schedule and Package wise schedules.
  • Submitting planning package to client for review and approval.
  • Developing project applicable WBS (work breakdown structure) and project wide activity codes.
  • Resource loading and levelling at EPC level and presenting to management to avoid any future resource crunch.
  • Package wise Resource monitoring for achieving the schedule.
  • Package wise S-Curve Development and Monitoring for entire project.
  • Controlling project schedule by identifying critical path, project interfaces and schedule driving parameters.
  • Maintaining engineering progress and procurement register.
  • Development of Progress Reports on Daily basis, Weekly basis and Monthly basis.
  • Active participation in Daily Progress Meeting, Project Review Meeting weekly and monthly basis.
  • Project includes following:
  • Cooling Water Piping, Sea Water Piping, Fire Water Piping and different Closed Drain Piping’s with different other systems.
  • Project also includes Different Rotating equipments, Static Equipments and Heat Exchangers.
  • Cooling Water Piping, Sea Water Piping, Fire Water Piping and different Closed Drain Piping’s with different other systems.