Construction Project Planner / Senior Planner, Volker Laser, Ross Planning contract for VolkerLaser (directly as worked with them previously, see below) – M1 River Trent Viaduct Column Strengthening, programme reorganisation in MS Project
START Date:
February, 2017
END Date:
March, 2017 The existing programme had some spurious link as the order of works had been dragged from an existing resourced programme, I sorted out the order and linking, and submitted this to VL for consideration, after 3 iterations this was submitted to their Client. The initial plan was for me to update this over several months, however this request was never made by VL
- Company:
- Industry:
- Job Role:
- Project:
- Region:
- Skills & Expertise: